DMRC’s MD Indicates Heritage Line to Now Open Only After Holi

If you’ve been following along, then this shouldn’t come as a surprise.

Speaking with The Hindu’s editorial team in Delhi, the Delhi Metro Rail Corporation’s Managing Director Mangu Singh has indicated they’ll be able to open the 5.17 km ITO – Kashmere Gate extension of the Violet Line, also known as the Heritage Line, only after the festival of Holi on March 13.

Excerpt from The Hindu:

“We are not in a hurry to open half done stations,” Mr. Singh said, referring to Phase II when many stations were opened to the public even before all the work was completed. Speaking about the much-delayed and much-awaited ‘Heritage Corridor’, which will link ITO and Kashmere Gate metro stations, Mr. Singh said the line was unlikely to open before Holi on March 13. “It is almost ready but needs fire clearance and clearance from the Commissioner for Metro Rail Safety. It is a sensitive issue as other agencies are involved, it is not in our hands,” he said.

For one, I’m glad he’s straight-up admitted that the stations are not ready, as the Kashmere Gate Station has quite some interior finishing work pending before it becomes presentable and safe for public use – see lots of images here.

Map of ITO – Kashmere Gate section of Delhi Metro’s Violet Line – view Delhi Metro Phase 3 map & information

Recent images from inside the Jama Masjid Station can be seen here. Here’s a new image of the Delhi Gate Station’s platform which I recently shared on Twitter:

Delhi Gate Station – Photo Copyright: DNA

And here are some images of the entry/exit structures shared by a Twitter follower:

Jama Masjid Station

Lal Qila Station

As I’ve previously highlighted in the January 2017 update post, with the way things are going at Kashmere Gate and the NATM tunnels north of it, where trains still haven’t entered for testing, this line is heading towards a Q2-Q3 commercial opening.

For more updates, check out the Delhi section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

24 Responses to "DMRC’s MD Indicates Heritage Line to Now Open Only After Holi"

  1. Anonymous says:

    So it will be a race between this line and magenta :p

    Reply
  2. Aby k says:

    Magenta line may open in Q2,nsic station way behind other stations

    Reply
  3. Siddhant Kumar says:

    What is the meaning of the words you write in your posts q2 q3.

    Reply
  4. Siddhant Kumar says:

    What is the meaning of the words you write in your posts q2 q3

    Reply
  5. Tanmay says:

    Its quarter 2 or 3.

    Reply
  6. Mridul yadav says:

    what is the progress on the southward extension of violet line form Escorts mujesar to Ballabhgarh????

    when it is expected to open.

    Reply
    • TMRG says:

      No recent update on that line – I’ll have to check with the contractor’s engineers to see what’s up. I expect it to open in 2018.

      Reply
  7. Arpit says:

    Have they started the work on connecting the new station with the existing one at Kashmiri gate. Was there yesterday, couldn’t see any development on that front.

    Reply
  8. bipin says:

    DMRC has now officially declared march as opening date

    Reply
  9. Aby k says:

    Yup,heritage may open in march but kalkaji to kalindi may open in q2-q3

    Reply
  10. Rishav Mahapatra says:

    will any part of phase 3 open in march-may period ?

    Reply
  11. CP says:

    Vilot line was schedlued to open from June 2016. It was postponed to August then Oct then diwali then new year then Feb and now March. And no surprise if it is delayed further. In the time of Mr Shridharan all metro projects were completed in time.The new CMD ofDMRC has no hurry but people are egarly waiting fort he hetitage line to commence from kashmere gate to make their journey comfortable.I hope DMRC willstict to March commtment. There is of course hurry. We cann’t justify repeated deferment looking at the poorctransport system in Delhi.

    Reply
  12. bipin says:

    I believe March deadline will also be missed by DMRC as Stations at Kashmere Gate and Lal Killa is still under construction

    Reply
  13. Metro says:

    This corrupt motherfucker of a moron mangu singh is leading metro to a downward spiral. he’s corrupt to every cell of his body.

    Reply
  14. Lalit says:

    When will Noida sector 62 extn to blue line be complete? It is very slow even without land acquisition problems.

    Reply
    • TMRG says:

      Expecting that to open in 2018. A section from the City Centre to Sec-71 might open by the end of this year so that NMRC can start operations on their line from Sec-71 to Gr. Noida.

      Reply
  15. Nitish says:

    Will violet line extension start around holi or still there is more time?

    Reply
    • TMRG says:

      Give it more time. Expecting it to open in Q2 (April-June) as there’s quite some work left at Kashmere Gate.

      Reply
  16. bipin says:

    Kasmere Gate and Lal Quila Station Construction is still going on. Whether Metro is going to revise opening date again even after delay of more than 24 months

    Reply
    • TMRG says:

      Good question! They’ve been really quite so far. Only if the media nudges them will they offer a new deadline, which I believe would be around May-June.

      Reply