L&T-STEC JV Completes Casting 1000 Tunnel Rings for Mumbai Metro
This weekend, Larsen & Toubro and Shanghai Tunnel Engineering Company (L&T – STEC) JV announced the completion of casting work for a 1000 tunnel rings which will form the twin tunnels of Mumbai Metro’s 33.5 km Line-3 between Cuffe Parade & Aarey Colony.
These tunnel ring segments will be erected by three TBMs (Wainganga 1, 2 & 3) exclusively for tunnels on the 4.157 km package UGC-07 located on the northern end of the line between CSIA Terminal 2 – Marol Naka – MIDC – SEEPZ – Sariput Nagar Ramp. A tunnel ring is typically 1.4 m wide, and consists of 5 segments + 1 ‘key’ segment. For the entire 33.5 km line, approximately 40,000 rings will be cast for all 7 civil packages.
Some images of L&T-STEC’s yard on the Jogeshwari–Vikhroli Link Road (JVLR) –
In a separate announcement, they’ve revealed that TBM T-206 “Wainganga-1” (commissioned on January 8) has completed erecting 100 rings from the Pali Ground Shaft towards CSIA Terminal 2 Station –
Parts of TBM D215 ‘Wainganga-3’ are currently being lowered into the Pali Ground Shaft, while parts of TBM D213 ‘Wainganga-2’ have been stationed near the Sariput Nagar Ramp waiting for the shaft to get ready.
For more updates, check out the Mumbai section of The Metro Rail Guy!
– TMRG
Please send me updates
You can subscribe to notifications here –
https://themetrorailguy.com/2017/01/04/new-feature-subscribe-to-notifications-for-new-posts/
Not Interested…..hehehehehehheee
google it…..hehehhzhzhzhzhhhehehehe
I am working as a faculty in NICMAR. Helpful in teaching.
Not required…..hehehheheheheee
Contracts were awarded for the second part of Line 2-B and parts of Line 4 of Mumbai Metro
Yeah, I’ve updated the two posts on the lowest bidders for each line with information. Also just posted a map with the current status of all lines here –
https://twitter.com/TheMetroRailGuy/status/971400269215956994
hehehehhehehehehe
I m building materials supplier
I m supply for aggregate,solid block,washed sand,river sand,etc.
Any requirement plzzz contact me
Patel:-8976299787
Are any of the contracting company implementing BIM(Building Information Modelling) technology in the construction or design phase?
Cam put garautear and tapering all cam nolage com