Paras Railtech Awarded Delhi Metro Grey Line’s Tunnel Work
The Delhi Metro Rail Corporation (DMRC) on Tuesday awarded Paras Railtech with a Rs. 43.92 crore contract for constructing a 289.65 meter cut and cover tunnel (Package CC-126A) on the 1.218 km Najafgarh – Dhansa Bus Stand extension of Delhi Metro’s Grey Line.
This underground tunnel of the Phase 3 project’s Package CC-126 was originally awarded to Shanghai Tunnel Engineering Co. Ltd. – SUCG Infrastructure India Pvt Ltd (STEC – SUCG IN JV) in October 2017, and tunneling breakthroughs were recorded by the team using one tunnel boring machine (TBM) on January 18 and June 26, 2019.
As shared earlier – my industry sources indicate that a construction site collapse had occurred in July on a 90 meter wide cut and cover portion due to heavy rainfall and ingress of water at the extreme western end of the line, and due to that the DMRC removed a 289.65 meter portion of the up-line tunnel’s construction from STEC – SUCG IN JV’s scope of works.
![](https://themetrorailguy.com/wp-content/uploads/2020/10/DelhiMetroCC126ALOA.png)
DMRC invited bids for this tunnel’s pending work on September 21 with an estimate of Rs 48.99 crore and opened technical bids on October 13 to reveal two bidders – Paras . Financial bids were opened on October 24.
Financial Bid Values:
Firm | Bid |
Paras Railtech Pvt. Ltd. | Rs. 43.92 crore |
Pragati Construction Consultants | Rs. 54.81 crore |
Completion Period: 4 months
Brief Scope: Construction of Cut and Cover tunnel box from Chainage 5050.35 (UP Line) to 5340.00 (UP line) for extension of Dwarka Najafgarh Metro Corridor of Delhi MRTS Phase-III (view detailed project scope)
![](https://themetrorailguy.com/wp-content/uploads/2020/09/DelhiMetroGreyLineMap2.jpg)
Back in September, Paras Railtech also won the track-work contract for the Airport Express Line’s 1.878 km extension to Dwarka ECC Station.