Mumbai Metro’s TBM Surya-1 Records Breakthrough at Hutatma Chowk
Moments ago, Tunnel Boring Machine XRE 2114-408 (Surya-1) operated by the Larsen & Toubro – Shanghai Tunnel Engineering Company (L&T – STEC) JV made a breakthrough at Hutatma Chowk Station’s southern-end on Mumbai Metro’s 33.5 km Aqua Line (Line-3).
This was TBM Surya-1’s third (and penultimate) breakthrough, 4.25 km Package UGC-01’s 6th of 8 (earlier 7) planned breakthroughs for the Cuffe Parade – CST section, and overall Line-3’s 34th of what will now be 42 (earlier 41) planned breakthroughs.
This Robbins Crossover XRE TBM with a 6.65 meter diameter was originally launched from Cuffe Parade to build Line-3’s up-line tunnel, and recorded breakthroughs at Vidhan Sabha Station in April 2019 and Churchgate Station in October 2019.
For its third of four assignments that ended today – the machine was recommissioned from Churchgate in January 2020 and traveled 649m to build Line-3’s up-line tunnel.
Last month, TBM Surya-2 recorded a breakthrough at the NATM-mined tunnel on the down-line (shown on the left in the above graphic), while today’s breakthrough by Surya-1 was recorded at the adjacent cut and cover station-box.
More on details on the unique Hutatma Chowk Station can be viewed here.
Here’s a status of package UGC-01 between Cuffe Parade and CST stations where 2 breakthroughs are now pending, both at CST Station. This table is best viewed on a desktop device –
TBM | Line | From | To | Distance | Status |
1 | Up | Cuffe Parade | Vidhan Bhavan | 1128m | Completed |
1 | Up | Vidhan Bhavan | Churchgate | 498m | Completed |
1 | Up | Churchgate | Hutatma Chowk | 649m | Completed (This Post!) |
1 | Up | Hutatma Chowk | CST | 551m | Yet to Begin |
2 | Down | Cuffe Parade | Vidhan Bhavan | 1254m | Completed |
2 | Down | Vidhan Bhavan | Churchgate | 481m | Completed |
2 | Down | Churchgate | Hutatma Chowk | 653m | Completed |
2 | Down | Hutatma Chowk | CST | 556m | Yet to Begin |
With 34 breakthroughs completed, there are now 8 more breakthroughs pending on Mumbai Metro’s Line-3:
Package | Section | Distance, Status |
UGC-01 | Hutatma Chowk – CST (up-line) | 551m, Not Started |
UGC-01 | Hutatma Chowk – CST (down-line) | 556m, Not Started |
UGC-03 | Science Museum – Mahalaxmi (up-line) | 1118m, In Progress |
UGC-03 | Mahalaxmi – Mumbai Central (up-line) | 837m, Not Started |
UGC-03 | Science Museum – Mahalaxmi (down-line) | 1136m, In Progress |
UGC-03 | Mahalaxmi – Mumbai Central (down-line) | 830m, Not Started |
UGC-04 | Siddhivinayak – Dadar (down-line) | 1126m, In Progress |
UGC-06 | Sahar Road – CSIA T1 (up-line) | 1516m, In Progress |
Contractors on Package UGC-04 (definitely) and UGC-06 (likely) will record their final breakthroughs by the end of the year. All tunneling works are expected to be completed only in Q4 2021 if no major hiccups arise.
For more updates, check out the Mumbai section of The Metro Rail Guy!
– TMRG
TMRG, is the tunneling work going mostly on schedule for this line?
Barring package UGC-07 (northern-most), tunneling is delayed across all packages, especially on package UGC-03. Contractors aren’t worried though because of the depot issue and resulting Line-3 – Line-6 integration rework.