Extraction Work Begins for Pune Metro’s TBMs at Civil Court
Workers from Gülermak – Tata Projects Limited JV earlier this month began extracting two tunnel boring machines from Pune Metro Line-1’s crossover cavern at the Civil Court Interchange Station.
These Ø6.52m Terratec earth pressure balance machines, Mutha (S78) and Mula (S79), had recorded breakthroughs at the cavern’s western-end in September-end and early-November respectively after tunneling about 1438m from the College of Agriculture Shaft.
Those TBM breakthroughs on the 16.589 km Line-1 (Purple Line) were #3 and #4 recorded for the team’s 3.78 km Package UGC-01 as well as the entire 6.52 km underground section of the 31.254 km Pune Metro Phase 1 project.
The scissor crossover cavern is 155 meters long and was built using the New Austrian Tunneling Method (NATM), making the breakthroughs among the most unique type in India. Back in October, L&T – STEC also recorded a similar breakthrough into a NATM tunnel built for Mumbai Metro’s Hutatma Chowk Station.
Over the next few months, both TBMs will be placed on to cradles (visible in the snaps above) and then moved to the other end of the Civil Court station using hydraulic jacks over a distance of roughly 280 meters (indicated by the pink arrow below).
From Civil Court, these TBMs will embark on their final assignments for Package UGC-01 towards Budhwar Peth Station, a distance of about 800 meters. En route both machines will pass right underneath Mutha River, at a depth of about 10 meters below the riverbed. That may happen only by Q2 2021 though as Budhwar Peth is one of the most congested neighborhoods of the city and building the station’s TBM retrieval shaft will take time.
One or both TBMs may in the future be involved in building Package UGC-02’s tunnels between Budhwar Peth – Mandai – Swargate along with TBM S81, but that remains to be seen.
For more updates, check out the Pune section of The Metro Rail Guy!
– TMRG
Can you tell me ahmedabad metro phase 2 contracts C1 and C2 awarded aur not
I’ve asked industry friends – no one knows. If I had to guess, I’d say no.
Hello Team,
Any latest updates on Hinjawadi-Shivajinagar metro route work?
Piling work have just started for this metro line. If things go well, then the line should be open by mid 2023. But currently they are facing some challenges such as land acquisition for depot, pending Right of Way etc, which should be sort out ASAP
Snaps/video of a piling – in case anyone’s interested: https://themetrorailguy.com/2020/11/19/tata-siemens-begins-piling-for-pune-metros-line-3/
Clevin – even without those challenges, mid-2023 would be incredibly tough 🙂 Currently I see it opening no sooner than Q4 2024. Still early days though, so let’s see how things progress.
Hi TMRG,
1)A article came early this year that Bihar Government had planned to connect both the international airport of patna under the phase 2 of patna metro..??
2)They also included that a branch line will be made near Patna zoo to the airport(forming a station for airport).
3)Can you please name the station of patna metro which are coming under phase 2 ( i.e:-Bihta Airport and naubatpur)??
4) Please clarify me if this information provided by me(mostly from internet article) are real or fake.
It’s very early to talk about phase 2. Nothing is final for phase 2 as of now
Exactly!