Tata JV Wins Mumbai-Ahmedabad Bullet Train’s PMC Contract

June 17 Update: TCE – Aarvee – CEG – Padeco JV was today issued a LOA by NHSRCL to provide project management consultant (PMC) services.

March 22 Original Post:

Tata Consulting Engineers – Consulting Engineers Group – Aarvee Associates – PADECO Co. JV today emerged as the lowest bidder to provide project management consultancy services for the civil construction of the 508.17 km Mumbai – Ahmedabad High Speed Rail (MAHSR Bullet Train) project.

India’s National High Speed Rail Corporation (NHSRCL) had invited tenders (bids) for the PMC service’s contract on November 11 based on the Quality and Cost Based Selection (QCBS) method.

Technical bids were opened in December-end 2020 to reveal 3 bidders. Within those, two consortia qualified after technical evaluation was completed last week where the Tata JV also scored the highest technical score.

Financial Bid Values:

FirmBid (JPY + INR)
Tata Consulting Engineers – Consulting Engineers Group – Aarvee Associates – PADECO Co. JV1364,830,000 JPY + 1014,94,15,952 INR
Nippon Koei – Oriental Consultants Global Co. – RITES JV1,865,298,944 JPY + 1182,86,82,673 INR

Package: NHSRCL/CO/CA/MA-SVGC/2020/34

Brief Scope: Project Management Consultancy Services for Construction of Civil Works Packages of Mumbai Ahmedabad HSR

Indicative alignment of Mumbai – Ahmedabad High Speed Rail (Bullet Train) Project – view Mumbai Ahmedabad HSR info & route map

Tata JV’s bid works out to be approximately Rs. 1111 crore. When awarded, they will be onboard with a tenure of 96 months.

Per NHSRCL’s press release, their scope will include supervision for all 13 civil works packages including viaducts, concrete / steel bridges, tunnels (undersea & mountain tunnels), civil work of all 12 stations, maintenance depots, and Training Institute building.

NHSRCL last week tweeted that more than 110 piling machines and other construction related machinery are now at work on the 237 km Package C4 which runs from the Maharashtra / Gujarat border near Vapi to Vadodara. Although late, the appointment of a dedicated PMC team will now greatly help manage, provide oversight and leadership to NHSRCL in executing the project.

For more updates, check out my Home Page!

– TMRG

written by

Global traveler who prefers mass rapid transit

40 Responses to "Tata JV Wins Mumbai-Ahmedabad Bullet Train’s PMC Contract"

  1. RK Mishra says:

    Congrats

    Reply
  2. Hari Puttar says:

    congrats to Tata Consulting Engineers – Consulting Engineers Group – Aarvee Associates – PADECO Co. JV

    till now how many pillars piling done how many pile caps and pillars casted ??

    Reply
  3. Hari Puttar says:

    bhai tumhare isme comment jo time dikhata hai na usme kuch gadbad hai

    Reply
  4. Rajashekhar says:

    Kudos to TCE’s infra cluster!

    Reply
  5. Anjani Kumar Singh says:

    Heartiest congratulations to Team

    Reply
  6. Srinivas Avvaru says:

    Congratulations to all TCE-Aarvee-CEG-PADECO team…Kudos ✌✌✌

    Reply
  7. v.v.Krishna Reddy says:

    Congratulations to the well qualified team

    Reply
  8. Dr.M.Chandrasekhar says:

    Hearty congratulations to the TCE JV and wish they bring out the best project in the Country to make an example for many such projects as required across the Nation.

    Reply
  9. JAGGIREDDYV says:

    A great project for modern India.

    Reply
  10. Nilesh says:

    Great news Heartiest Congratulations…..

    Reply
  11. Dileep Sharma says:

    Congratulations Tata team

    Reply
  12. Abhishek kapadia says:

    Any update related to Job vacancy in Bullet train project?

    Reply
    • TMRG says:

      Not sure. I did hear about a potential conflict of interest situation arising earlier though, but thought that was sorted.

      Reply
  13. Deep shah says:

    Latest update is that lowest L2 Nippon Koie may get awarded due to TCE’s Conflict of Interest.

    Reply
  14. Yogesh says:

    What is update about pmc st NHSRCL

    Reply
  15. Rohit Yadav says:

    Is there any update regarding deployment of PMC staff ?

    Reply
  16. Yogesh says:

    Any update about pmc?

    Reply
  17. Bhanu Gaikwad says:

    Happy to be the part of the Project project

    Reply
  18. shahu rajesh says:

    job work

    Reply
  19. Abhishek kapadia says:

    Design, Manufacture, Supply, Construction, Installation, Testing and
    Commissioning of 2 x 25 kV Power Supply Electrification System (Traction
    Substation, Overhead Equipment and MV/LV Power Distribution
    Equipment), along with Associated Buildings for these Systems and related
    equipment in training institute on Design Build Lump Sum Price Basis for the
    Construction of Mumbai-Ahmedabad High Speed Rail
    (Package No. MAHSR – EW-1)

    Any information?

    Reply
  20. Pratap yadav says:

    Hello
    I’m pratap yadav

    Shree hole enterprise
    Vehicles service provider
    Innova
    Scorpio
    Ertiga
    Bolero
    Suv
    TUV
    any vehicle requirement plz content

    Reply
  21. Nitin K says:

    Which companies got Power supply & traction work as a general consultant ???

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to Hari Puttar Cancel reply

Your email address will not be published. Required fields are marked *