Work Begins on Mumbai-Ahmedabad HSR’s Anand-Nadiad Station

Larsen & Toubro and its subcontractor ‘Zed Geotechnics and Construction’ on Friday kicked off construction work for Anand-Nadiad Station of the 508.17 km Mumbai – Ahmedabad High Speed Rail (MAHSR Bullet Train) project.

L&T’s team had started basic site preparation works in February. On Friday morning, they held a bhoomi puja and started test piling work during which a piling rig bored and lowered a 1800mm diameter pile cage vertically to a depth of 28 meters.

Snaps shared by followers Prasad Zantye & Abhishek Khade:

Anand-Nadiad station lies on civil Package C6 (chainage 401.898 to 489.467) – the third longest of the entire line which connects Vadodara with Ahmedabad through one station and a minor depot at Anand-Nadiad. Its exact location is just south-west of Utarsanda Railway Station, close to Nadiad – view exact location.

Indicative alignment of Package C6 between Vadodara – Anand/Nadiad – Ahmedabad – view Mumbai Ahmedabad HSR info & route map

Package C6’s Rs. 7,289.00 crore contract was awarded by the National High Speed Rail Corporation (NHSRCL) in November 2020 after L&T emerged as its lowest bidder in October. L&T is chasing a 1,370 days (3.75 years) deadline and started piling work in March 2021 at Rayka Village near Vadodara.

Preliminary Design of Anand-Nadiad Station – Copyright: NHSRCL
28m Test Pile Cage

A list of all bullet train civil packages and their status can be viewed here.

For more updates, check out the High Speed Rail section or my Home Page!

– TMRG

written by

Global traveler who prefers mass rapid transit

13 Responses to "Work Begins on Mumbai-Ahmedabad HSR’s Anand-Nadiad Station"

  1. Anirudh Kulkarni says:

    https://youtu.be/IDHZTVZ9aaI. In this video their is a board at the beginning which says Date of completion is 02/10/2024 i.e 2nd October 2024. Bro do you think it is achievable or nhsrcl is being too optimistic ??

    Reply
    • TMRG says:

      That’s just for C6’s civil work. Construction practicalities will push civil completion beyond that date.

      Reply
  2. Saket says:

    Any news on land acquisition of Maharashtra section?

    Reply
  3. Hoshi says:

    The bullet train project fails to connect all district headquarters on its route and its economic viability
    is in question as the traveling public will prefer fast trains on the existing routes.

    Reply
  4. Pratham says:

    Hi, is DMRC’s new girder launcher true. Can you explain it with some pics!!

    Reply
  5. Shubham pathak says:

    Hame kaam chahiye mere paas messon helper sariya satering team available he

    Reply
  6. Hiren khalasi says:

    pl. say where the anand-nadiad station will actually made at ??

    Reply
  7. DINESH VANIA says:

    Hello sir..

    We are from Gujarat travels daily bus available for MUMBAI, PUNE ,AURANGABAD ,PUNE ,BENGLORE ,KOHLAPUR ,NASIK ,HYDERABAD ,SOLAPUR

    FOR,BOOKING PLEASE CONTECT OR MAIL

    7096222000
    DINESH VANIA

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to TMRG Cancel reply

Your email address will not be published. Required fields are marked *