Bangalore Metro’s TBM Varada Restarts Tunneling to Langford Town

Tunnel Boring Machine S-1264 operated by Afcons Infrastructure on Thursday was recommissioned at Rashtriya Military School Station for building the down-line tunnel of Bangalore Metro’s 21.386 km Pink Line (Nagawara – Kalena Agrahara).

Nicknamed Varada, this is TBM S-1264’s second and final drive for the 3.655 km Package RT-01 (Rashtriya Military School Station – Dairy Circle Ramp) of the 73.92 km Bangalore Metro Phase 2 project.

This refurbished Herrenknecht earth pressure balance (EPB) machine was originally commissioned in March 2021 from Rashtriya Military School Station (near Vellara Junction) to build the 596 m up-line tunnel towards Langford Town where it recorded a breakthrough in November 2021. The machine’s parts were then brought back to RMS Station to build the parallel down-line tunnel.

RT-01: Dairy Circle Ramp – National Military School- view Bangalore Metro Phase 2 Info & Map

Per the tunneling plan, Afcons hopes to complete tunneling on this section in 235 days.

Segment for 1st ring being erected

Last week TBM Vamika arrived in the middle of Dairy Circle Station after recording a hidden breakthrough at the station box’s southern-end earlier in the month. Here’s a snap of Vamika (S-1260) and TBM Rudra (S-1259) which is undergoing minor refurbishment at the moment.

In the coming months, both will be recommissioned one after the other towards Lakkasandra Station to build 747.338 meter tunnels which Afcons hopes to complete within 243 days.

For more updates, check out the Bangalore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

2 Responses to "Bangalore Metro’s TBM Varada Restarts Tunneling to Langford Town"

  1. Sriharsha says:

    So we can expect many breakthrough this year on this line. However the work on the elevated section is very slow.

    Reply
  2. Balaji says:

    The work on this Pink line is in full swing. Looks like the new contractor JR Infra is taking things seriously after simplex failed and delayed this by over 2 years. The pillars and connections have been completed from Hulimavu arch to before Rainbow hospital. The portion in front of Vega Mall is now being built. However there are still some portions where digging has still not started upto Dairy circle, Eg. Opp mosque, jayadeva hospital etc. I don’t see this line starting anytime before 2026.

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *