L&T & J Kumar Awarded Delhi Metro Silver Line’s Tunneling Contracts
Larsen & Toubro and J Kumar Infraprojects on Wednesday were awarded 2 underground tunneling contracts (DC-09 & DC-08) of the 65.1 km Delhi Metro Phase 4 project‘s 23.622 km Silver Line.
Both firms had submitted the lowest revised bids in mid-February after the Delhi Metro Rail Corporation (DMRC) internally re-invited price bids from the technically qualified bidders of the original round.
Both packages come with a 42 month deadline and are being financed by JICA through a Rs. 8,390 crore ODA loan.
Package DC-08
This 6.116 km Aerocity – Kishangarh section is on the western-end of the 23.622 km Silver Line and comprises of 4 stations at Aerocity, Mahipalpur, Vasant Kunj and Kishangarh.
- DMRC’s Estimate: Rs. 1349 crore
- Awarded to: J Kumar Infraprojects (JKIL)
- Final Contract Value: Rs. 1611.74 crore (INR 1426,99,50,000 + USD 2,45,00,000)
Brief Scope: Design and Construction of Twin Tunnel (Up & Down Line) by Shield TBM, Cut and Cover Tunnel box and four Underground stations namely Aerocity, Mahipalpur, Vasant Kunj and Kishangarh with Entry/Exits & Connecting subways from chainage (-) 760 mt. to 5356.285 mt. of Aerocity to Tughlakabad Corridor of Phase-IV of Delhi MRTS.
DC-08’s design details such as crossover locations, TBM launching shafts and Aerocity Station’s design, in relation to the upcoming Delhi – Alwar RRTS Line, can be viewed here.
Package DC-09
This 6.51 km section, with twin-tunnels smack-dab in the middle of the Silver Line will connect Kishangarh Station’s east-end (chainage 5356.285) with a ramp (chainage 11867.000) west of Saket G Block Station through 4 stations at Chhattarpur (interchange with Yellow Line), Chhattarpur Mandir, IGNOU and Neb Sarai.
- DMRC’s Estimate: Rs. 1428 crore
- Awarded to: Larsen & Toubro (L&T)
- Final Contract Value: Rs. 1737 crore (INR 1533,50,10,000 + USD 2,70,00,000)
Brief Scope: Design and Construction of Twin Tunnel (Up & Down Line) by Shield TBM, Cut and Cover Tunnel box, Underground Ramp and four Underground stations namely Chhattarpur, Chhattarpur Mandir, IGNOU and Neb Sarai with Entry/Exits & Connecting subways from chainage 5356.285 mtr. to 11867.000 mtr. of Aerocity to Tughlakabad Corridor of Phase-IV of Delhi MRTS.
DC-09’s design details such as crossover and ramp locations can be viewed here.
With this exciting development, all 4 JICA-funded underground packages of Phase 4 have now been awarded! Basic ground work on DC-07 by Afcons started recently, and I see work on the rest starting latest by May.
Civil Package | Status |
Package DC-05: Derawal Nagar to RK Ashram, 7.46 km underground section with 6 stations | Awarded to Afcons Infra |
Package DC-08: Aerocity to Kishangarh, 6.11 km underground section with 4 stations | Awarded to J Kumar |
Package DC-09: Kishangarh to Saket G-Block, 6.88 km underground section with 4 stations | Awarded to L&T |
Package DC-07: Sangam Vihar to Tughlakabad, 6.477 km underground section with 3 stations | Awarded to Afcons Infra |
See a list of all Delhi Metro Phase 4 packages and their status here.
For more updates, check out the Delhi Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.
– TMRG
What’s update on Mumbai Metro line 3 last 2 Tunneling ? How much it has progress ? And much meters to go before breakthrough ?
Don’t have progress numbers, but hear both TBMs are stuck.
Where are the TBM stuck?
Great. When can the ground work be expected to start?
What about Agra and Kanpur ? When to get LOA?
Im Civil Contractor Please mail me for this work
Great.when can the ground work be expected to start civil work
Hi, I just wanted to ask if you will be covering the tendering process of the Vande Bharat trains as they are also in the Semi-HSR category.
Not actively tracking right now
Any job requirements for je please contact me
Earlier in 2021 these 2 packages were awarded to Tata Projetc – DC-08 and AFCONS DC-09 correct???