L&T Wins Chennai Metro Phase 2’s Track Work Contract
July 29 2022 Update: Larsen & Toubro has been awarded a contract by CMRL valued at Rs. 339,63,37,733.00
April 11 2022 Original Post: Larsen & Toubro today emerged as the lowest bidder to supply and install standard gauge tracks for Chennai Metro’s Line-3 and Line-5 (Package BC-3,5/TRK-02) after Chennai Metro Rail Ltd (CMRL) opened financial bids.
Both these new lines of Chennai Metro’s 118.9 km Phase 2 project will run in a north-south orientation to connect Madhavaram – SIPCOT (45.813 km Line-3) and Madhavaram – Sholinganallur (47 km Line-5) with a mix of elevated & underground stations.
CMRL invited tenders for this systems contract, financed by JICA, in October 2021 with a 850 day deadline + 730 day (DLP) and an unknown estimate. Technical bids were opened in February to reveal 6 bidders.
Financial Bid Values
Firm | Bid (Rs. Crore) |
L&T | 342.13 |
Vijay Nirman Company (VNC) | 382.09 |
Texmaco Rail and Engineering | 395.21 |
Rail Vikas Nigam (RVNL) | 399.44 |
ITD Cementation India | 404.28 |
IRCON International | 414.79 |
Brief Scope: Supply, installation, testing and commissioning of track works of standard gauge including all associated works in (a) elevated section between CMBT (excluding) and ELCOT (including) in corridor 5 – upto circular connection to corridor-3 and (b) elevated section between Sholinganallur (excluding) to SICPOT (including) in Corridor 3 and pocket tracks & stabling lines of Chennai Metro rail Project Phase-2
Like other Phase 2 packages, CMRL’s estimate for this is unknown, so I can’t provide an assessment on how L&T’s bid is placed and what the next steps look like.
Things on the systems tendering front are moving along nicely. Back in January, IRCON was awarded a similar track-work contract for Line-4. In February, CMRL received 2 bids for lines 3 & 5’s head-hardened rail contract from Mitsui and Ohmi Industries.
This is the first major systems contract for both lines where financial bids have been opened. A list of all Chennai Metro Phase 2 civil & system packages and their status can be viewed here.
For more updates, check out the Chennai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.
– TMRG
Hey tmrg!
ITD cementation started ground works for orange line 4 near lighthouse (Marina beach).
Just posted: https://themetrorailguy.com/2022/04/11/itd-begins-work-on-chennai-metro-line-4s-underground-section/
Hey TMRG, will BMRCL also open similar bids for the blue line in the coming weeks?
Blue Line’s system tendering hasn’t started yet. Notices are nowhere to be seen.