Siemens JV Wins Surat Metro’s Electrification Contract EP-1

Siemens -RVNL JV on Monday emerged as the lowest bidder for commissioning the 750 V DC Third Rail electrification system of Surat Metro Phase 1 project.

The city’s 40.35 km Phase 1 consists of two lines with 37 stations. Financial bids for the final civil packages were opened last summer, with Line-1’s 11.6 km Dream City Depot – Kadarsha ni Nal section taken up on priority. Following that, all tendering activity moved to the systems side.

Gujarat Metro Rail Corporation (GMRC) had invited tenders for this major systems contract, financed by Agence française de développement (AFD), in February 2022 with an unknown estimate and deadline. Technical bids were opened in May 2022 to reveal 7 bidders.

Financial Bid Values

FirmBid (Rs. Crore)
Siemens-RVNL JV672.96
KEC International699.08
Larsen & Toubro (L&T)748.33
TEECL – ABL JV905.22
Kalpataru – Gulermak JVDisqualified (Fin Bid Not Opened)
Sterling and WilsonDisqualified (Fin Bid Not Opened)
Linxon IndiaDisqualified (Fin Bid Not Opened)

IFB No: GMRCL/TR/ST/EP-1/2022

Brief Scope: Supply, Erection, Testing and Commissioning of Power Supply receiving & Distribution System, 750 V DC Third Rail Traction electrification and SCADA System for Surat Metro Rail Project phase-I

Route Map of Surat Metro’s Phase 1 project – view Surat Metro information & map

GMRC’s budgeted estimate remains unknown to me, so I can’t provide an assessment on the chances of a contract getting awarded. We’ll have to wait and watch to see how this plays out.

A list of all Surat Metro packages and their status / contractors can be viewed here.

For more updates, check out the Surat section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

4 Responses to "Siemens JV Wins Surat Metro’s Electrification Contract EP-1"

  1. Pankaj Gupta says:

    The budget for the package was 529Cr.The prices are 27% higher than budget.All project last year have been awarded within 10% of budget.How can GMRC make an incorrect budget.

    Reply
  2. Tunnels says:

    Consulting firms are a source of blunders.

    Aecom egis systra louis Berger DB OCG NK PADECO AYESA are mere for money laundering and hawala trades.

    Reply
  3. Abhishek kapadia says:

    Please share job related information related to respactive projects.

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to Pankaj Gupta Cancel reply

Your email address will not be published. Required fields are marked *