L&T’s 1st Chennai Metro Phase 2 TBM Kaveri Starts Tunneling

Larsen & Toubro on Thursday commissioned S-1327A – their 1st of 8 tunnel boring machines for the 118.9 km Chennai Metro Phase 2 project at Chennai’s Greenways Road Station

This 100m long Ø6.65m Herrenknecht earth pressure balance (EPB) machine nicknamed TBM Kaveri along with 7 other TBMs will construct approximately 12 km twin tunnels (total 24 km) on the new 45.813 km Line-3 between Kellys and Taramani Road Junction stations.

For its first assignment, the machine from Greenways Road will bore 1.226 km southwards towards Adyar Junction Station which CMRL hopes to complete in August 2023. Along the way it’ll bore under Adyar River near Thiru Vi. Ka. Bridge.

Launch event stage – Photo via a follower

The machine had passed factory acceptance tests (FAT) in July 2022 at Herrenknecht’s local facility in Chennai and L&T’s team began lowering its parts into the Greenways TBM Launch Shaft in January 2023.

L&T was awarded Package TU-02’s Rs. 2385 crore contract by Chennai Metro Rail Ltd. (CMRL) in May 2021 with a 42 month deadline.

Scope of TU02: Construction of approximately 12 km twin bored tunnels (total = 24 km) from Kellys Station to Taramani Road Junction and the construction of diaphragm walls, entry/exit structures of Chetpet station, Royapettah Government Hospital Station, Thiruvanmiyu Station, and part diaphragm wall of Greenways Road Station, including launching and retrieval shafts at the above stations.

Line-3’s underground section: Venugopal Nagar – Kellys – Taramani Road Junction | Map via Chennai Metro Rail Ltd. includes my edits
Greenways Road Station site – Photo via Zeelani Mohammed

The machine’s back-up gantry will be lowered and attached for the main-drive later.

Photo via CMRL

In the coming months TBM Kaveri’s sister machine, TBM Adyar (S-1326A), will begin tunneling works to build the parallel tunnel. Besides these 2 machines, L&T will deploy 4 new CRCHI machines and 2 refurbished Robbins machines from Mumbai Metro Line-3’s Package UGC-01.

Overall, this is the 4th of 23 TBMs in Phase 2 to start tunneling after Tata Projects’ TBM S96 & TBM S97 from Madhavarm Milk Colony towards Madhavaran High Road, and TBM S98 towards Venugopal Nagar.

For more updates, check out the Chennai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

5 Responses to "L&T’s 1st Chennai Metro Phase 2 TBM Kaveri Starts Tunneling"

  1. Vijayadurai says:

    this is Music to ears. 🙂

    Reply
  2. Kamal Babu⁸ says:

    Hi
    When is royapettah chennai tbm will be implemented pls update

    Reply
  3. Ram vissa says:

    When can expect to start the work of radhakrishna salai station.

    Reply
  4. Vijayadurai says:

    Hello

    What is the status of Kaveri today. It was supposed to be in Adyajuntion by August

    Can you share some updates pls

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *