Kanpur Metro’s TBM Nana Records Final Breakthrough at Chunniganj

Gulermak – Sam India Builtwell JV today celebrated tunnel boring machine (TBM) S93’s final breakthrough at Chunniganj Station of the 32.4 km Kanpur Metro Phase 1 project.

This was TBM S93’s fourth and final tunnel breakthrough and the 7th of 8 breakthroughs planned in the project’s 3.619 km long Package KNPCC-05 connecting MacRobertganj Ramp – Nayaganj Station.

This 6.52m diameter and 120m long Terratec TBM, nicknamed Nana after Nana Saheb Peshwa, was deployed to build a portion of the up-line tunnel of Kanpur’s 23.785 km Line-1 (IIT Kanpur – Naubasta). Its fourth drive was completed in roughly 70 days.

Here’s a list of all drives completed by TBM Nana so far:

  • Bada Chauraha to Nayaganj (1025m) – December 2022
  • Chunniganj to Naveen Market (748m) – June 2023
  • Naveen Market to Bada Chauraha (516m) – September 2023
  • MacRobertganj to Chunniganj (420m) – February 2024 (this post!)
Photo by UPMRC

Uttar Pradesh Metro Rail Corporation (UPMRC) had awarded Gulermak – Sam India with Package KNPCC-05’s construction contract in March 2021 with a 36 month deadline.

Besides constructing twin tunnels, they’ll be building 4 stations at Chunniganj, Naveen Market, Bada Chauraha and Nayaganj, each 215m long.

Route of Kanpur’s first underground section (Ramp – Nayaganj) with the exact location of stations enroute – view Kanpur Metro route map & information
Photo by UPMRC

With this development, Line-1’s upline tunnel has been built all the way from MacRobertganj Ramp to Nayaganj – a distance of roughly 3.6 km including 3 cut & cover station boxes.

TBM Nana will now be dismantled, stored and likely get deployed for tunneling again in early 2025 at Kanpur Metro Line-2’s underground Package KNPCC-11 which was awarded to Kalpataru Projects International Ltd. – Gulermak JV in December 2023.

Gulermak – Sam’s 2nd TBM (S92 nicknamed Tatya) working on the down-line tunnel was re-commissioned from MacRobertganj Ramp a few weeks after TBM Nana. I haven’t heard of any major issues being encountered, so we should expect its final breakthrough to happen around mid-March.

For more updates, check out the Kanpur section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

3 Responses to "Kanpur Metro’s TBM Nana Records Final Breakthrough at Chunniganj"

  1. JOYANTA says:

    I heard that KPIL is going to purchase new HK TBM for Kanpur UG project.

    Reply
  2. Hover says:

    The Tender was awarded on 9.03.2021 with deadline of 36 months. It’s march 2024 already and still 1 breakthrough and finishing works are remaining. Is there going to be some sort of penalty on sam/gulermak or does it simply work this way. Or is it just cos of government/UPMRC babus?