Ceigall Awarded Agra Metro’s AGCC-05 Contract for Sikandra Link
Besides Kanpur Metro KNPCC-12’s contract, Ceigall India Ltd. (CIL) was today awarded a Rs. 266.94 crore contract for the civil construction work of Package AGCC-05 on 14.25 km Agra Metro Line-1 (Taj East Gate – Sikandra) by Uttar Pradesh Metro Rail Corporation (UPMRC).
This 3.725 km elevated section of 29.40 km Agra Metro Phase 1 project will link RBS Ramp in Khandari and Sikandra via 3 elevated stations at ISBT, Guru Ka Taal & Sikandra – all located along national highway NH-19 (old NH-2).
This package is located on the northern-end of the line and is the third & final package for Line-1 main-line’s construction work.
UPMRC had invited bids for AGCC-05’s contract in November 2023 with a Rs. 296.78 crore estimate and 24 month deadline. Technical bids were opened in February to reveal 5 bidders, while financial bids were opened this Wednesday.
Financial Bid Values (Recap)
Firm | Bid (Rs. Crore) |
Ceigall India Ltd. | 315.00 |
NCC Ltd. | 346.72 |
PNC Infratech Ltd. | 353.46 |
HG Infra Engineering Ltd. | 358.11 |
Dineshchandra R Agrawal Infracon Ltd. | 383.40 |
UPMRCL’s Brief Scope: Design and Construction of elevated viaduct and 3 Nos. elevated stations (viz. ISBT, Guru Ka Taal & Sikandra Metro Station) including Civil, Associated and Ancillary Structure, Architectural Finishes, Water Supply, Sanitary Installation, Drainage, External Development, Fire Fighting, Fire Detection, E&M works and PEB structures of Balance Section chainage (-) 42.96 m to 3682.941 m of Corridor-1 of Agra Metro at Agra, Uttar Pradesh, India.
UPMRC took just two days from opening financial bids to awarding the contract – something that’s unheard of in other metro organizations.
As shared in Kanpur’s post, both are Ceigall’s first contracts in the metro construction space and their experience primarily lies in the highway / expressway indsutry – see examples on my site here.
With this development, I expect Ceigall to begin basic ground towards the end of Q2 2024 (April – June) and full fledged construction work in Q3 2024 (July – September).
Contractors for all sections of Agra Metro’s 14.25 km Agra Metro Line-1 (Taj East Gate – Sikandra) have now been assigned.
- AGCC-01: Sam India Builtwell (Operational)
- AGCC-02: Afcons Infrastructure – Sam India JV (part operational & under construction)
- AGCC-05: Ceigall India (Contract Awarded – this post!)
A full list of all Agra Metro civil & system packages and their status can be viewed here.
For more updates, check out the Agra section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
NCC emerges L1 bidder for Pune Riverfront Project from Wakad Bypass to Sanghvi Bridge for Rs. 318Cr
J Kumar was L2 at 330Cr
Cool
Damn this UPMRC is so fast in execution of contracts and it’s metro projects
But it seriously needs to expand the Lucknow metro and takeover Noida metro operations
Other metro companies need to work like UPMRC , others are always slow!
Agreed. Looking forward to seeing how how they fare with Lucknow’s Line 2
@TMRG, Bengaluru Metro additional 2 corridors approved by the Karnataka State Govt. Did you check it out?
Yup, saw a blurb about it
Want to know about agra metro line 2 map
I was expecting a metro station at khandari (Shashtri nagar poposed)to be also constructed alongside the existing construction work. Would be eazy to construct now then later