12 Bidders for Pune Ring Road’s 9 Construction Contracts

12 civil engineering firms have submitted a total of 26 bids to construct the 136.80 km Pune Ring Road project after bids were opened on Thursday.

This 4-6 lane access-controlled highway project by Maharashtra State Road Development Corporation (MSRDC) will be developed under 9 packages (E1, E2, E3A & E3B, E4, W1, W2, W3, W4 & W5). It has been designed with a 120 kmph speed limit and will connect the taluks of Khed, Haveli, Purandhar, Bhor, Mulshi and Maval.

MSRDC had invited RfQ applications for Pune Ring Road’s civil construction in April 2023 and opened bids in June 2023 to reveal 28 firms had submitted applicatios. 18 of those firms qualified to the next RfP round in December 2023. MSRDC then invited price bids from those 18 firms in January 2024 with a construction deadline of 900 days.

Bidders

  • Afcons Infrastructure: W2, W3 & W4
  • APCO Infratech: E4
  • Gawar Construction: W5
  • GR Infraprojects: E4 & W5
  • H.G. Infra Engineering Ltd.: E2 & W5
  • J Kumar Infraprojects: E2
  • Larsen & Toubro Ltd.: E2
  • Megha Engineering and Infrastructures Ltd.: E1, (E3A & E3B), W1, W2 & W3
  • Navayuga Engineering Company Ltd.: E1, (E3A & E3B), W1, W2, W3 & W4
  • PNC Infratech: E2 & E4
  • Roadway Solutions India Infra: E4
  • Welspun Enterprises: E2

Package (Length) & Chainage

  • PRR E1 (11.85 km): 0.650 to 12.500 – Village Urse to Village Indori in Mawal Tahsil
  • PRR E2 (13.80 km): 12.500 to 26.300 – Indori to Chimbali Tq Mawal and Khed
  • PRR E3A & E3B (21.20 km): 26.300 to 47.500 – PRR E3A: Chimbali to Solu Tq Khed; PRR E3B: Solu to Lonikand Tq Khed and Haveli
  • PRR E4 (24.50 km): 47.500 to 72.000 – Village Lonikand Near Village Walti Tq Haveli
  • PRR W1 (14.65 km): -0.650 to 14.000 – Urse to Village Kemsewadi in Tq Maval Mulshi
  • PRR W2 (20.00 km): 14.000 to 34.000 – Village Kemsewadi to Village Morewadi in Tq Mulshi
  • PRR W3 (14.00 km): 34.000 to 48.000 – Morewadi to Village Vardade Khamgaon Maval in Tq Mulshi and Havel
  • PRR W4 (7.50 km): 48.000 to 55.500 – Vardade Khamgaon Maval to Village Kalyan Rahatwade in Tq Haveli 
  • PRR W5 (9.30 km): 55.500 to 64.800 – Kalyan Rathwade to Shivare Kusgaon Phase Tq Haveli Bhor
Alignment of Pune Ring Road and its 2 sections (WRR and ERR) – via MSRDC

The upcoming 700 km Pune – Bangalore Expressway project by National Highways Authority of India (NHAI) will have its northern terminal at Pune Ring Road.

Technical evaluation is not required in this round as that’s what the RfQ round was for. Financial bids will most likely be opened only after the Lok Sabha election’s model code of conduct ends. Stay tuned to see who wins each package!

MSRDC on Thursday also opened bids for 179.85 km Jalna – Nanded Expressway and 126 km Virar-Alibaug Multi-Modal Corridor projects. Check out each link to see bidder and package information.

For more updates, check out the Expressway section or my Home Page! Sign up for free instant email notifications on new posts over here. Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

3 Responses to "12 Bidders for Pune Ring Road’s 9 Construction Contracts"

  1. Girish Adya says:

    Good to hear with ring route concept traffic issues & Problems will ease out

    Reply
  2. Amol Mujumdar says:

    Along with this, Pune needs a northern ring road also. That would split the traffic coming in to Chakan towards east and west parts of pune. As of now if you are coming to Pune from Nashik in the evenong, you reach Rajgurunagar very smoothly, and then the traffic kills as Chakan starts.

    Reply
  3. Chidambar Joshi says:

    Badly required for a metro city like Pune.

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *