14 Bidders for Mumbai Multi Modal Corridor’s 11 Construction Contracts

14 civil engineering firms have submitted a total of 33 bids to construct 96.47 km Phase 1 of the 126 km Virar-Alibaug Multi-Modal Corridor (VAMMC) project after technical bids were opened on Thursday.

This access-controlled highway project by Maharashtra State Road Development Corporation (MSRDC) will connect Navghar and Balavali in Phase 1. It will be developed under 11 packages (MMC-1, MMC-2, MMC-3, MMC-4, MMC-5, MMC-6, MMC-7, MMC-8, MMC-9, MMC-10, MMC-11).

The expressway will consist of 8 to 14 lanes and connect three districts – Raigad, Thane, and Palghar.

MSRDC had invited RfQ applications for its civil construction in April 2023 and opened bids in June 2023 to reveal 28 firms had submitted applications. 18 of those firms qualified to the next RfP round in December 2023. MSRDC then invited price bids from those 18 firms in January 2024 with a construction deadline of 900 days.

Bidders

  • Afcons Infrastructure: MMC-4
  • APCO Infratech: MMC-2
  • BSCPL Infrastructure: MMC-10 & MMC-11
  • Gawar Construction: MMC-11
  • GR Infraprojects: MMC-3 & MMC-4
  • IRCON International Ltd. MMC-6, MMC-7 & MMC-8
  • J Kumar Infraprojects: MMC-8, MMC-10 & MMC-11
  • Larsen & Toubro: MMC-4, MMC-5, MMC-6 & MMC-7
  • Megha Engineering and Infrastructures: MMC-1, MMC-3 & MMC-9
  • Montecarlo: MMC-6 & MMC-7
  • Navayuga Engineering Company: MMC-1, MMC-5 & MMC-9
  • Oriental Structural Engineers: MMC-2, MMC-3 & MMC-8
  • PNC Infratech: MMC-5
  • Welspun Enterprises: MMC-2, MMC-3, MMC-10 & MMC-11

Package (Length) & Chainage

  • MMC-1 (8.27 km): 0.065 to 8.335
  • MMC-2 (12.39 km): 8.335 to 20.720
  • MMC-3 (5.28 km): 20.720 to 26.000
  • MMC-4 (3.26 km): 26.000 to 29.260
  • MMC-5 (11.5 km): 29.620 to 40.760
  • MMC-6 (12.83 km): 40.760 to 53.592
  • MMC-7 (8.61 km): 53.592 to 62.200
  • MMC-8 (7.97 km): 62.200 to 70.167
  • MMC-9 (7.23 km): 70.167 to 77.400
  • MMC-10 (11.22 km): 77.400 to 88.620
  • MMC-11 (7.85 km): 88.620 to 96.470
Alignment of Virar – Alibaug Multi-Modal Corridor around Mumbai – view project information page

Technical evaluation is not required in this round as that’s what the RfQ round was for. Financial bids will most likely be opened only after the Lok Sabha election’s model code of conduct ends. Stay tuned to see who wins each package!

MSRDC on Thursday also opened bids for 179.85 km Jalna – Nanded Expressway and 136.80 km Pune Ring Road projects. Check out each link to see bidder and package information.

For more updates, check out the Expressway section or my Home Page! Sign up for free instant email notifications on new posts over here. Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

18 Responses to "14 Bidders for Mumbai Multi Modal Corridor’s 11 Construction Contracts"

  1. Kartik says:

    You inserted a wrong paragraph above the bidders section. Copy paste from previous post ? 😂

    Reply
  2. Girish Adya says:

    Data incorrect

    Reply
  3. Girish says:

    Destroying eco system on the name of development. Huge loss to konkan forest and wildlife. Go out of green zone, there is lots of baren land in India that need development.

    Reply
    • James says:

      That would defeat the purpose of building it near Mumbai as the whole point is to boost economic growth and reduce logistics cost in the greater Mumbai area.

      Reply
    • guest says:

      People who believe this must first move out of MMR and start living in trees with minimal needs. Otherwise such namesake enviornmentalists are found in dozens for a dime !

      The ecosystem damage is directly proportional to population. show any place in world where modern, developed, comfortable city exist without touching nature

      Reply
  4. Sunil says:

    Even smaller cities like bangalore/hyderabad/chennai already have broad Ring Roads, while here, Mumbai and Pune is yet to get one. It’s a crying shame as far as road planning goes.

    Reply
    • Parmesh says:

      You are correct. Is there any update on much delayed East West connector Vikhroli – Ghansoli link road bridge which was earlier in the design stage by N P Bridging of Belgium?
      It’s a shame if such projects are shelved by the authorities and Government.

      Reply
  5. Nilesh says:

    Any update on Karanja rewas bridge

    Reply
  6. Chouhan Nilesh says:

    Has anybody noticed how there’s exactly 3 bidders for each package except PKG 1,9.

    Reply
  7. Kamal Lalla says:

    Recently i was driving on new roads constructed.
    Design and Engineering needs a big change.
    Roads are having too much of curvatures and because of this at designed speed while driving it gives too much discomfort.
    When we are designing new highways and high speeds then we have to eliminate curvatures .
    I understand Implementation agency finds lot of difficulty in acquiring land for roads construction.Still we need to do justice on investments.

    Reply
  8. amit kulkarni says:

    Hello, How can i get package wise requirement of steel for this project ?

    Reply
  9. Darshak says:

    Who is the GC or PMC from client for this project

    Reply
  10. Sunil says:

    In the virar end it should be connected to the planned coastal road.

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *