3 Bidders for Mumbai Metro’s Dongri Depot on Red Line (CA-207)

Three civil engineering firms have submitted bids to construct Mumbai Metro Red Line‘s Dongri Depot after the Mumbai Metropolitan Region Development Authority (MMRDA) opened technical bids on Tuesday.

Dongri Depot & Workshop under Package CA-207 is proposed to come up on 41.36 hectares of land (view on Google Maps) in north-west Mumbai. This facility will be built to stable and maintain BEML trains for the entire Red Line (Line-9, Line-7 & Line-7A) connecting Dongri – Mira Bhayandar – Dahisar East – Gundavali – CSIA Terminal 2.

Besides an Operations Control Centre (OCC), Dongri Depot will consist of a 690m long test track with platforms, stabling shed (SBL) with 20 lines (with room for 18 future lines), workshop shed (WSL) area with 3 lines, an inspection shed (IBL) area with 4 lines, receiving substation (RSS) and two auxiliary substations (ASS).

MMRDA had invited bids for the depot’s construction in February 2024 with a Rs. 626.69 crore estimate and 52 months (4.3 year) construction deadline.

Bidders

  • KPC Projects Ltd.
  • NCC Ltd.
  • Ritwik Projects Pvt. Ltd.

Brief Scope: Depot land development works and Construction of Depot Infrastructures Comprising Stabling Yard, Operation Control Centre, Depot Control Centre, Administrative Building, Maintenance and Inspection buildings, Auxiliary substation, Road, underground utility duct, Drainage System and Rainwater Harvesting etc. complete (including Architectural Finishing ,Plumbing and PEB Works) for CAR Depot at Dongri for Metro Line- 9 of Mumbai Metro Rail Project of MMRDA

Dongri Depot’s layout – via MMRDA’s tender documents

The bids have now been sent for technical evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor.

As shared in the past – the contract’s duration at 52 months is unusually long since the site currently comprises of a hill which will have to be levelled. The package’s scope identifies the ‘land development’ component will include cutting, filling, preparatory works, tree transplantation and soil stabilization.

Access to the Dongri Depot will require a 4.9 km long extension of Line-9 on Uttan Road from Subhash Chandra Bose Ground Station. Here’s an alignment of the extension prepared by Line-9’s Detailed Design Consultant (DDC) Archom – Veritas – LKT Engineering JV in June 2023:

Alignment of Line-9’s extension and Dongri Depot – via MMRDA’s CRZ submission (includes my labels)

Back in September 2023, MMRDA formally submitted an application to obtain Coastal Regulation Zone (CRZ) clearance for this extension’s construction which will feature 2 new elevated stations at Murdha and Rai Goan. A tender notice for their construction is currently pending.

It goes without saying but once Dongri Depot is built, all Red Line BEML train-sets currently stabled & maintained at Line-2’s operational Charkop Depot and the under construction Mandale Depot will move to Dongri Depot.

For more updates, check out the Mumbai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

8 Responses to "3 Bidders for Mumbai Metro’s Dongri Depot on Red Line (CA-207)"

  1. Aryan says:

    1) Any Update on Mumbai Metro L2B Half Height PSD tender? which was invited by DMRC. MS-04. I didn’t find it in your Yellow Line Tenders & Updates.
    Btw many Technical & Financial Bids opened of L2B Yellow line after Model Code of Conduct ended your page especially Yellow line one needs update.
    2) Local Media is saying atleast 3 months wait for Kanjurmarg Land.
    3) On 2nd July 5 bids will be opened unless they decide to extend the date.
    4) Mumbai Metro Line 12 work is in great speed.
    https://youtu.be/BnPJFAzK1jw?si=R_eCPU9kpu4YaDFF
    Here ☝️is the update on Casting Yard of Metro L12

    Reply
    • TMRG says:

      1) Missed writing about MS-04, but that was awarded to Zhuzhou CRRC Times Electric in July 2023. I’ve now updated Yellow Line’s page with all the information I have. Let me know if you have any further updates on specific contracts.

      2 & 4) Cool. As much as I love the rains, I can’t wait for them to end so things pick up

      3) Which ones? I only see Line-2B lifts & escalators (CA-162)

      Reply
      • Aryan says:

        1) Thanks TMRG for the update on Line 2B PSD MS-04 Tender was looking for it since long 🙏.
        2) Now they are not revealing the Bidders Names & Winners Name. Looks like you have some Great Sources.
        3) They again Extended the Deadline.

        Reply
  2. vivaan k says:

    Any update on MM3? RDSO rolling stock trials just finished, so I was expecting a July-end opening, but recent updates show a September opening

    Reply
    • TMRG says:

      There’s pending architectural finishing work inside some of the stations. I’ve seen recent snaps and the signage is disappointingly small.

      Before CMRS, at least the following are needed:

      Speed Certificate from RDSO (likely received by MMRC)
      Schedule of Dimensions (SoD) certificate from RDSO (likely received by MMRC)
      Fire Department’s NOC for each station after mock-fire demo
      Independent Safety Assessment (ISA) certificate

      Reply
      • Aryan says:

        As per some of the media Reports Mumbai Metro Line 3 Phase 1 from Aarey to BKC Deadline is now December 2024.

        Reply
  3. S.S.Gunjal says:

    Respected sir,
    Iam possessing 38 years of Railways Traction experience,my parent Railway is Central Railway Mumbai division.if i will get any opportunity to serve with any engineering organisations I will work with full of my capacity please

    Reply
  4. Aseem says:

    There are several private lands in the middle of the car shed land. How will MMRDA give access to the owners of these lands and how will it achieve the hill levelling (cutting of the hill by 10mtrs) without touching these private lands?

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *