Mumbai Metro Line-3’s Final TBM Breakthrough Recorded by Tansa 1

What a moment. Tunnel Boring Machine 1238 operated by Doğuş-Soma JV on Wednesday afternoon arrived at Mumbai Central Station on Mumbai Metro’s new 33.5 km Line-3 (Aqua Line).

This historic 42nd and final tunnel breakthrough was recorded by a Robbins machine nicknamed Tansa 1. It was its 3rd breakthrough and Doğuş-Soma JV’s 6th breakthrough planned for package UGC-03 tunnels connecting Worli and Mumbai Central stations.

Photo via Abhishek Mishra

This Ø6.65m Robbins slurry machine had previously achieved a breakthrough at Mahalaxmi Station in August 2021. It was then was recommissioned in October 2021 for its final assignment to build the 837m up-line tunnel towards Mumbai Central Station, which was completed in 243 days using 558 concrete rings.

Route of Aqua Line’s Package UGC-03 (Mumbai Central – Worli) – view Mumbai Metro information & map
Waiting… – Photo via Abhishek Mishra
Done! – Photo via MMRC
Photo via Abhishek Mishra

A video posted by MMRC can be viewed here.

With this development, all 54.5 kms of TBM-bored tunnels (up-line and down-line) for Line-3 have been completed using 17 machines – all the way from Colaba in the south to Sariput Nagar Ramp, near Aarey Colony Station, in the north. The only tunneling works left are minor mining works for a total of 91 emergency cross-passages.

Here’s a table displaying UGC-03’s tunneling plan and status of each tunnel (best viewed on a desktop device).

TBMLineFromToDistanceStatus
1UpScience MuseumWorli2072mCompleted Jan 2020
1DownScience MuseumMahalaxmi1136mCompleted August 2021
1UpMahalaxmiMumbai Central837mCompleted Nov 2022 (this post!)
2DownScience MuseumWorli2057mCompleted March 2020
2UpScience MuseumMahalaxmi1118mCompleted July 2021
2DownMahalaxmiMumbai Central832mCompleted June 2022

On the Aqua Line’s information page, I’ve got a section with details of final breakthroughs recorded on all 7 civil packages of the line.

MMRC is now chasing a December 2023 deadline to commission the Sariput Nagar Ramp – Bandra-Kurla Complex section. That of course depends on the completion of Aarey Depot where construction work still has to resume.

The assignment of a new contractor to build its sheds is pending, so meeting that timeframe seems unlikely to me. Depot issues aside, with pending civil, system and architectural work – I see the entire line becoming operational no sooner than Q3 2024. I’ll take this because half a year ago the entire line’s future was uncertain. Cheers!

For more updates, check out the Mumbai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

6 Responses to "Mumbai Metro Line-3’s Final TBM Breakthrough Recorded by Tansa 1"

  1. Gaurav says:

    Hey TMRG

    For mamma metro’s purple line I read that steel girders coming all the way from chattisgarh were being placed over railway tracks at tin factory. The expected completion was around Dec,2022 for placing all the girders. Any update on how is that going and when will the Tin Factory gap be plugged?

    Reply
  2. Shiv says:

    Woooohooo!

    Reply
  3. Nilay says:

    Great!!

    Reply
  4. Rahul says:

    Expressway ka update dalo bro

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *