6 Bidders for Agra Metro Line-2’s AGCC-07 Elevated Contract

Six firms today submitted bids for civil construction contract AGCC07 of Agra Metro Phase 1 project’s 15.09 km Line-2 which will connect Agra Cantonment and Kalindi Vihar via 14 stations.

This mega package by Uttar Pradesh Metro Rail Corporation (UPMRC) includes the construction of the entire line’s viaduct, 14 elevated stations, 530m viaduct to Line-2’s Kalindi Vihar Depot, and interestingly a 2.61 km viaduct from north of Sadar Bazar metro station to Line-1’s PAC Depot built by Lisha Engineers as part of Package AGCC-03.

Its scope includes the entirety of Package AGCC-06 (Agra Cantt – Sanjay Place) which was abruptly scrapped by UPMRC in October 2023 and absorbed into Package AGCC-07’s scope.

At Agra College Station users will be able to interchange and switch over to the city’s 14.25 km Line-1 (Sikandra – Taj East Gate) where an underground station is under construction by Afcons – SAM India JV as part of Package AGCC-02.

UPMRC had invited bids for AGCC-07’s construction in December 2023 with a Rs. 1529.29 crore estimate and tight 24 month deadline. Technical bids were opened today.

Bidders

  • Afcons Infrastrucure Ltd. (AIL)
  • Ceigall India Ltd. (CIL)
  • DBL – Evrascon JV
  • Larsen and Toubro Ltd. (L&T)
  • NCC Ltd.
  • T and T Infra Ltd.

Brief Scope: Design and Construction of Main Line Elevated Viaduct from Agra Cantt. Metro Station to Kalindi Vihar Metro Station [Chainage (-77m) to 15016m] including Viaduct Connection with Ramp (Chainage 0.00m to 2610m) from (nearby) Sadar Bazar Metro Station to existing Corridor-1 Depot at PAC ground & Corridor-2 Depot Entry/Exit lines Viaduct with Ramp (Chainage 0.00m to 530m) and 14 nos. of Elevated Stations i.e., Agra Cantt, Sadar Bazar, Pratap Pura, Collectorate, Agra College, Hariparvat Chauraha, Sanjay Place, M.G. Road, Sultanganj crossing, Kamla Nagar, Ram Bagh, Foundary Nagar, Agra Mandi & Kalindi Vihar metro stations including Civil, Associated Ancillary Structures, Architectural Finishes, Water Supply, Sanitary Installation, Drainage, External Development, Fire Fighting, Fire Detection, E&M works and PEB structures in Corridor-2 of Agra Metro at Agra, Uttar Pradesh, India

Package AGCC-07 (Agra Cantt. – Kalindi Vihar) with key stations marked –  view Agra Metro Phase 1 route map & information
Southern section of Agra Metro’s Line-2 (earlier part of Package AGCC-06)

The bids have now been sent for technical evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor.

This contract will be financed by the European Investment Bank (EIB) through a €450 million loan approved in December 2021.

At 15.09 km, this is currently the second longest civil package in India’s metro history after Mumbai Metro Line-12’s 22.17 km long Package CA-240 which was won by Gawar Constructions in February 2024.

This is the 5th civil package of Agra Metro’s Phase 1 project to enter the technical bid evaluation stage. The only tender notice pending now is for Line-2’s Kalindi Vihar Depot in north-east Agra which might not be built due to the 2.61 km inter-line viaduct from Line-2 to PAC Depot. Time will tell.

See a list of all Phase 1 packages (civil & systems) and their status over here.

For more updates, check out the Agra section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

3 Responses to "6 Bidders for Agra Metro Line-2’s AGCC-07 Elevated Contract"

  1. Abbas says:

    Plan for Kalindi Vihar depot will be scrapped as UPMRC is planning to build a new depot for this line adjacent to current depot on land near Commisioner’s Office. There is a plan to connect Line 1 depot with Line 2 via single track for now while Line 2 will also have dedicated ramp to new depot.

    Reply
  2. Jaideep Singh says:

    Agra metro ke corridor 2 ka civil construction kab tak shuru hoga please reply jaroor karna request bhai

    Reply
  3. Vinod gudge says:

    Any update on this tender?? When will the bids open???

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *