Geomardy Wins Mumbai Metro Line-11’s Geotechnical Contract

Geomarine Dynamics India Pvt. Ltd. (Geomardy) was today declared as the lowest bidder for conducting geotechnical soil investigation for 18 km Mumbai Metro Line-11 (Green Line) which will connect Anik Bus Depot – SPM Chowk via 15 underground stations.

The alignment of Mumbai Metro’s underground Line-11 was redesigned by Mumbai Metro Rail Corporation Ltd. (MMRC) earlier year. When built, it will be Mumbai city’s third underground line after Line-3 (Aqua Line) & Line-7A (Red Line).

The objective of this geotechnical investigation is to have sufficient data on the sub-soil to assist with preparing detailed design of structures, and use appropriate machinery, methods & technology during construction. This will also help ensure least possible damage to existing structures during the construction phase.

MMRC had invited bids for this contract in early August with a 90 day deadline and an estimate of around Rs. 1.52 crore. Technical bids were opened by MMRC in August-end to reveal 11 bidders out of which 4 firms did not qualify.

Financial Bid Values

FirmBid (Rs. Crore)
Geomarine Dynamics India1.21
Genstru Consultants1.43
S & R Geotechniques1.47
CEG Test House And Research Centre1.63
Pureways Infra1.67
Monarch Surveyors & Engineering Consultants1.82
Myrtle Project And Consultancy1.97

MMRC’s Brief Scope: Geotechnical Investigation works for revised alignment of Mumbai Metro Line 11

Here’s a copy of Line-11’s revised alignment. 15 underground stations are planned to be built at Anik Bus Depot, Wadala Depot, CGS Colony, Ganesh Nagar, BPT Hospital, Sewri, Hay Bunder, Coal Bunder (Darukhana), Reay Road, Byculla, Nagpada Junction, Bhendi Bazaar, Crawford Market, CSMT Metro (interchange with Line-3 / Aqua Line), Horniman Circle, and SPM Circle.

Revised alignment of Mumbai Metro’s Line-11 from the Utility Survey’s tender notice

Geomardy’s bid of Rs. 1.21 crore was 20% below MMRC’s estimate of Rs. 1.50 crore, so a contract should be awarded in the coming weeks without a long financial bid evaluation period. That said, in Q1 2025 we should start seeing their barricaded work sites with investigation tripods along the line’s alignment.

Per MMRC’s tender notice, boreholes of 150mm for geotechnical investigation should be spaced at regular intervals of 500 meters along the twin tunnel’s alignment with 3 boreholes required at each station’s site area. These boreholes will be dug up to a depth of 10m, between 10-20m, and beyond 20m per the consultant borehole plan.

If and when awarded, Geomardy will need to submit the following in their final report:

  • Bore hole details and locations with georeferenced co-ordinates.
  • Area geology and related characteristics
  • Water table levels
  • Test results
  • Bore hole wise foundation recommendations
  • Cutoff value
  • Soil bearing capacities
  • Seismicity

As shared in the past, this investigation is one of the several steps MMRC has to take prior to construction which I envision will not start until at least 2027 – and that’s on the optimistic side of the spectrum.

Other necessary steps including securing financing, preparing detailed designs, appointing a General Consultant, appointing consultants for EIA, SIA & rehabilitation, and conducting the civil tendering process.

For more updates, check out the Mumbai Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

8 Responses to "Geomardy Wins Mumbai Metro Line-11’s Geotechnical Contract"

  1. Prince says:

    Any news on Metro Line 12?

    Reply
  2. Aryan says:

    Looks like MSRDC started awarding PRR & Jalna – Nanded E-Way Contracts. 2 contractor who were L1 bidder got LoA. No news on VAMMC & Samruddhi’s Eastern Extension

    Reply
    • TMRG says:

      Cool, thanks I saw a bunch of announcements to BSE. Will update the info pages of each project as and when contracts are awarded.

      Reply
  3. Mayur Mahajan says:

    Depot would be at Wadala? Or yet to be decided?

    Reply
  4. Sandeep says:

    Metro Line 4 and Metro Line 6 in Mumbai have been under construction forever. Most congested areas like JVLR, Ghodbunder road, LBS Road are suffering due to the incomplete projects. Trains are still overcrowded and nothing has changed for the past 30 years. Roads are not concretised, in spite of repeated announcements by our Transport minister.

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *