L&T’s Delhi Metro TBM-4 Records Breakthrough at IGNOU Station

Larsen & Toubro (L&T) today celebrated tunnel boring machine (TBM) DZ1124’s tunnel breakthrough at IGNOU Station of Delhi Metro’s 23.622 km Golden Line (Line-10) which will connect Aerocity – Tughalakabad via 15 stations.

This was TBM-4 (DZ1124)’s very first breakthrough and overall the fifth breakthrough for Delhi Metro Phase 4 project’s 6.51 km Package DC-09 connecting Kishangarh – Saket G Block.

DZ1124 is a 97m long CRCHI Earth Pressure Balance (EPB) machine and was commissioned in December 2023 to build the 1479m down-line tunnel from Chhattarpur Mandir Station to IGNOU Station.

DZ1124 built 1048 rings (1 ring = 1.4m) with an inner diameter of 5.8m at an average depth of 26m. Per the Delhi Metro Rail Corporation’s press release, the new tunnel has a minimum depth 15m and maximum depth of 36m, making it one of Delhi Metro’s deepest tunnels.

Waiting… – Photo by Sandip Mandal
Done! – Photo by DMRC

Delhi Metro Rail Corporation (DMRC) had awarded L&T with Package DC-09’s Rs. 1428 crore contract in March 2022 with a 42 month deadline.

Their 6.51 km section, with twin-tunnels in the middle of the Golden Line, will connect Kishangarh Station (chainage 5356.285) with a cut and cover ramp (chainage 11867.000) west of Saket G Block Station. It includes 4 stations at Chhattarpur (interchange with Yellow Line), Chhattarpur Mandir, IGNOU and Neb Sarai.

Alignment of Delhi Metro’s Golden Line (earlier Silver Line)’s Package DC-09 – view Phase 4 route map with all stations’ exact locations marked

DZ1124 is one of L&T’s four TBMs working on Package DC-09 between Kishangarh – Saket Ramp. The others are DZ1122, DZ1123 and DZ1125.

Photo by Sandip Mandal
Photo by Aritra Ari Mondal

This was the 5th of 10 breakthroughs planned in Package DC-09. L&T’s TBM-3 (DZ1125) working on the parallel tunnel was lowered and commissioned prior to TBM-4, but is now trailing behind by at least a month with its breakthrough now expected to take place in March.

TBM-1 (DZ1122) and TBM-2 (DZ1123) have each recorded two breakthroughs and were recently recommissioned from Neb Sarai Station to build roughly 730m tunnels towards the City Forest Ramp.

With today’s development, a total of 7 tunnel breakthroughs have been recorded so far for the Golden Line. From east to west: 2 by Afcons for Package DC-07, 5 by L&T for Package DC-09, and 0 by J Kumar on Package DC-08.

For more updates, check out the Delhi Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to all updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

13 Responses to "L&T’s Delhi Metro TBM-4 Records Breakthrough at IGNOU Station"

  1. Jimmy Vij says:

    What happened to J-Kumar ? Looks like their TBMs are stuck.

    Reply
  2. Diwakar kumar says:

    Hii
    Sir

    Reply
  3. Abhishek says:

    Technical Bids for Agra Gwalior opened on 25th with 10 bidders. Write a post about that also

    Reply
    • TMRG says:

      Do you have a list of bidders?

      Reply
      • Abhishek says:

        List of Bidders for Agra Gwalior on BOT
        DOTO: 25.02.2025
        Cost Estimate : Rs 4,262.78 Crore
        Length: 88.4 Km
        Bidders
        1. IRB Infra
        2. Adani Ent
        3. PNC Infra
        4. Dilip Buildcon
        5. D R Agarwal
        6. G R Infraprojects
        7. APSARA Pvt Ltd.
        8. MKC Infra
        9. Welspun
        10. Gawar Infra

        Reply
  4. Piyush Gautam says:

    Hello sir, why the Golden elevated section work too slow, any idea.

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *