TBM Makes 2nd Breakthrough at Delhi Metro’s Greater Kailash Station
Another one complete! 😀
Yesterday afternoon, the S890 Tunnel Boring Machine (TBM) operated by the Pratibha-FEMC team made a final breakthrough for the CC-23 project of Delhi Metro’s Phase 3 at the Greater Kailash station! This EPBM TBM was commissioned from the Chirag Delhi station on February 11 2016 and completed building the 545m long down-line tunnel of the new 38.235 km Magenta line which will connect Janakpuri West with Noida’s Botanical Garden by mid 2017. This was the 2nd breakthrough recorded here, with the 1st breakthrough taking place for the up-line tunnel a month ago.
Satellite view of the GK station’s shaft which is now partially covered:
TBM S883 which built the up-line tunnel and made a breakthrough last month can be seen here getting positioned to be dismantled:
June 6 update:
With this breakthrough out of the way, all twin tunnels between Kalkaji – Munirka (9 km) are now complete! Now only 3 more TBM breakthroughs are left for all tunneling works to be wrapped up on the Magenta Line:
Contract | Contractor | Origin | Destination | Tunnel |
CC-27 | L&T – SUCG | Shankar Vihar | Aravali Mid-Shaft | Down-line |
CC-27 | L&T – SUCG | Vasant Vihar | RK Puram Mid-Shaft | Up-line |
CC-27 | L&T – SUCG | Vasant Vihar | Munirka | Down-line |
As I mentioned towards the top of the post, this was the final breakthrough for project CC-23 which spans between Kalkaji – Nehru Enclave – Greater Kailash – Chirag Delhi – Panchsheel Park – Hauz Khas. A total of 10 breakthroughs were recorded and I’ve managed to track 8 of them since starting this initiative in July 2015. The 2 others between Nehru Enclave & Kalkaji took place in late 2014. Click on the post links below to relive each one of them:
Date | Origin | Destination | Distance | Tunnel | Post Link |
Aug 27 2015 | Hauz Khas | Panchsheel Park | 1.3 km | D/L | Click Here |
Oct 21 2015 | Hauz Khas | Panchsheel Park | 1.3 km | U/L | Click Here |
Dec 10 2015 | Chirag Delhi | Panchsheel Park | 635m | U/L | Click Here |
Feb 22 2016 | Greater Kailash | Nehru Enclave | 1095m | U/L | Click Here |
Mar 7 2016 | Chirag Delhi | Panchsheel Park | 635m | D/L | Click Here |
April 12 2016 | Chirag Delhi | Greater Kailash | 545m | U/L | Click Here |
May 19 2016 | Greater Kailash | Nehru Enclave | 1095m | D/L | Click Here |
May 25 2016 | Chirag Delhi | Greater Kailash | 545m | D/L | This Post! |
D/L=Down-line | U/L=Up-line
For more updates, check out the Delhi section of The Metro Rail Guy!
– TMRG
What is the status of the Terminal 1 station and when will the whole magenta line will be commissioned.
Hi, the station and its access tunnels connecting the domestic terminals are under construction. Entire line will open in phases between mid-end 2017.
What is the current status of the violet line’s kashmere gate extension ?
Tunneling works are complete. They’re working on covering up the shafts and building the entrance/exit structures. Station detailing works & track work are in advanced stage. Trial runs are supposed to begin in July.
Kasmiri gare violet line will be opened by august- september 2016. Trails are on the way
Any images? As per a recent announcement, DMRC said it’ll begin in July.