Ranjit Buildcon Begins Launching Segments for A’bad Metro’s Reach 4

On the night of April 6, Ranjit Buildcon commissioned their 1st launching gantry at AEC for building the 4.85 km elevated viaduct of Ahmedabad Metro’s Reach 4 section between Motera and Ranip in the northern part of the city. The contract for this section of the 17.23 km north-south line was awarded to Ranjit Buildcon on January 13, 2016 and ground-work began soon after in February. The section’s first pier was cast in December 2016 following which workers began setting up LG-1 in March – see images here and here.

After the 6 km Vastral – Apparel Park and 4.62 km Gyaspur – Shreyas sections, this is the third stretch of the metro project where segment launching work has started – see a map with sections here.

This stretch includes 5 stations at Motera, Sabarmati, AEC (Ahmedabad Electricity Company), Sabarmati Railway Station and Ranip for which a separate contract was awarded to the Pratibha – Ranjit JV in February 2017. When they begin piling work, all sections of Ahmedabad Metro’s 17.23 km north-south line will be under construction.

Alignment of Ahmedabad Metro's Motera - Ranip section

Alignment of Ahmedabad Metro’s Motera – Ranip section – view Ahmedabad Metro map & information

All set to begin launching – Photo Copyright: Akhilesh Shukla

Photo Copyright: Akhilesh Shukla

Photo Copyright: Akhilesh Shukla

Photo Copyright: Akhilesh Shukla

Photo Copyright: Nishan1502

Tweet from a follower showing the progress made:


Each segment weighs 40 tons and usually 10 segments are required to build one span between two adjacent piers. Here’s a snap from within their casting yard:

Photo Copyright: Prateek Jain

And here’s my go-to video to demonstrate how a Launching Gantry works its magic with precast segments to build modern segmental viaducts and bridges:

For more updates, check out the Ahmedabad section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

3 Responses to "Ranjit Buildcon Begins Launching Segments for A’bad Metro’s Reach 4"

  1. sabir says:

    9ice

    Reply
  2. Shashwat says:

    Any update in RS and signaling?

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to sabir Cancel reply

Your email address will not be published. Required fields are marked *