SUCG Subcontracted Mumbai Metro Line-3’s Partial Tunneling Works

Update: DOGUS-SOMA JV reached out with clarification. SUCG has been subcontracted tunneling works to expedite and match Mumbai Metro Rail Corporation Ltd. (MMRCL)’s schedule. There are various reasons for the delay, not at all pertaining to and beyond the control of Dogus-Soma JV. I offer my apologies for any confusion my original post may have caused.

Original Post (Now Modified):

SUCG Infrastructure India Pvt. Ltd. is confirmed to have officially been subcontracted tunneling works from Doğuş-Soma JV for the Mumbai Central – Mahalaxmi section of Mumbai Metro’s 33.5 km Line-3 (Aqua Line) which’ll connect Cuffe Parade – BKC – Aarey Colony through 27 stations.

This section is a part of the 5.06 km Mumbai Central – Worli package UGC-03 which is running terribly behind schedule with only 2 out of 6 breakthroughs accomplished by Doğuş-Soma JV’s Robbins slurry tunnel boring machines so far – both at Worli in 2020 (TBM 1238 / Tansa-1 in January & TBM 1239 / Tansa-2 in March).

SUCG’s scope of work includes building 837m up-line and 830m down-line tunnels between Mumbai Central and Mahalaxmi stations.

Route of Aqua Line’s Package UGC-03 (Mumbai Central – Worli) – view Mumbai Metro information & map

I heard rumblings of this subcontract as far back as January 2020 from industry insiders and it’s now been confirmed through a newly installed rolling gantry crane at the northern-end of Mumbai Central Station’s site which lists out SUCG’s name and logo.

SUCG’s crane recently installed at Mumbai Central Station
Closer look at the gantry crane with SUCG’s name and logo visible

This subcontracting of tunneling works is reminiscent of Bangalore Metro’s Phase 1 project where CEC-SOMA-CICI JV (contractor of Purple Line’s UG-1) was brought in to deploy a Hitachi Zosen slurry shield TBM for building a single 970 meter tunnel from Majestic Station to the North Ramp of the Green Line’s UG-2 in 2014-15.

Coming back to Mumbai, here’s a table displaying UGC-03’s tunneling plan (best viewed on a desktop device) and the status of each tunnel.

TBMLineFromToDistanceStatus
1UpScience MuseumWorli2072mCompleted Jan 2020
1UpScience MuseumMahalaxmi1118mPending
2DownScience MuseumWorli2057mCompleted March 2020
2DownScience MuseumMahalaxmi1136mPending
3UpMumbai CentralMahalaxmi837mPending
3DownMumbai CentralMahalaxmi830mPending

TBM 1238 (Tansa – 1) was transported as one unit from Worli back to Science Museum in March, and is currently waiting to be lowered into the station’s southern shaft. TBM 1239 (Tansa-2) is still sitting inside Worli Station and is waiting to be lifted out after its breakthrough in March.

We’ll have to wait and see when and which TBM SUCG will deploy to complete this assignment. Stay tuned to find out!

For more updates, check out the Mumbai section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

2 Responses to "SUCG Subcontracted Mumbai Metro Line-3’s Partial Tunneling Works"

  1. S MANIKANTAN says:

    When will the Cuffe Parade – Aarey Colony be realistically started? I am desperate to know, as I intend to travel from Kandivli to BKC by Metro,and I want it to come up at the earliest.

    Reply
    • TMRG says:

      Depends on when the Aarey Depot issue is solved. Whenever it is, add a minimum of 1.5 years. Tunneling works are behind schedule, but the depot (and the dependence of testing) is what will ultimately delay the line’s opening.

      Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *