Mumbai Metro’s TBM Surya-2 Records Breakthrough at Hutatma Chowk
On Friday, Tunnel Boring Machine Surya-2 operated by the Larsen & Toubro – Shanghai Tunnel Engineering Company (L&T – STEC) JV made a breakthrough at Hutatma Chowk Station’s southern-end on Mumbai Metro’s 33.5 km Aqua Line (Line-3).
This was Surya-2’s third (and penultimate) breakthrough, 4.25 km Package UGC-01’s 5th of now 8 (earlier 7) planned breakthroughs for the Cuffe Parade – CST section, and overall Line-3’s 33rd of what will now be 42 (earlier 41) planned breakthroughs.
This Robbins Crossover XRE tunnel boring machine (TBM) with a 6.65 meter diameter was originally launched from Cuffe Parade to build Line-3’s down-line tunnel, and recorded breakthroughs at Vidhan Sabha Station in May 2019 and Churchgate Station in October 2019.
For its third assignment that ended today – the machine was recommissioned from Churchgate in January 2020 and took 275 days to travel 653 meters while building 502 rings to arrive at Hutatma Chowk.
Interestingly, the breakthrough took place at the NATM-mined tunnel on the down-line, which was not part of the original tunneling plan as this TBM was supposed to pass through this section without recording a breakthrough. Post-tunneling, the plan was to dismantle the tunnel rings during NATM excavation. But it appears that in the interest of time, NATM work to house the station’s down-line tunnel and platform took precedence.
Surprisingly, Mumbai Metro Rail Corporation’s recent press release on October 7 also indicates the TBM should have passed through – see row #5 indicating Churchgate to CSMT (downline, 1233 m), so it appears there’s a disconnect between their communications/social media and the civil-works teams as this change in plans (to switch tunneling and NATM works around) must have taken place many moons ago.
More on details on the unique Hutatma Chowk Station can be viewed here.
TBM Surya-1 working on the parallel up-line was commissioned barely a week after Surya-2, so that should also make its breakthrough at Hutatma Chowk’s cut and cover box soon.
Here’s a status of package UGC-01 between Cuffe Parade and CST stations where 3 breakthroughs are still pending. This table is best viewed on a desktop device –
TBM | Line | From | To | Distance | Status |
1 | Up | Cuffe Parade | Vidhan Bhavan | 1128m | Completed |
1 | Up | Vidhan Bhavan | Churchgate | 498m | Completed |
1 | Up | Churchgate | Hutatma Chowk | 649m | In Progress |
1 | Up | Hutatma Chowk | CST | 551m | Yet to Begin |
2 | Down | Cuffe Parade | Vidhan Bhavan | 1254m | Completed |
2 | Down | Vidhan Bhavan | Churchgate | 481m | Completed |
2 | Down | Churchgate | Hutatma Chowk | 653m | Completed (this post!) |
2 | Down | Hutatma Chowk | CST | 556m | Yet to Begin |
With 33 breakthroughs completed, including this one with a change in plans, there are now 9 more breakthroughs pending on Mumbai Metro’s Line-3:
Package | Section | Distance, Status |
UGC-01 | Churchgate – Hutatma Chowk (up-line) | 650m, In Progress |
UGC-01 | Hutatma Chowk – CST (up-line) | 551m, Not Started |
UGC-01 | Hutatma Chowk – CST (down-line) | 556m, Not Started |
UGC-03 | Science Museum – Mahalaxmi (up-line) | 1118m, Not Started |
UGC-03 | Mahalaxmi – Mumbai Central (up-line) | 837m, Not Started |
UGC-03 | Science Museum – Mahalaxmi (down-line) | 1136m, In Progress |
UGC-03 | Mahalaxmi – Mumbai Central (down-line) | 830m, Not Started |
UGC-04 | Siddhivinayak – Dadar (down-line) | 1126m, In Progress |
UGC-06 | Sahar Road – CSIA T1 (up-line) | 1516m, In Progress |
For more updates, check out the Mumbai section of The Metro Rail Guy!
– TMRG
How can they remove the TBM inside the NATM tunnel, to reach other side of the station?. It seems to be a difficult task
It’ll continue building tunnel rings within the NATM tunnel. After it passes the station’s zone, they’ll demolish them.
Credit for this miscommunication goes to the MVA govt which replaced an efficient MD with an incompetent one jus for sake of ego. Interestingly, they had a huge propaganda of 9 more to go in all leading news papers a few days ago.
I saw that as well. I think it’s funny when operators supply the media with press releases and then celebrate the media coverage they receive.
I am working UGC-1 cuffprade to churchgate. I proude to L&T construction. Jai hind