Afcons Wins Kolkata Metro Line-6 Airport Section’s Work

Afcons Infrastructure today emerged as the lowest bidder among 4 to construct Kolkata Metro Line-6’s Package ANVS – a 3.519 km mostly elevated extension from Sub CBD-2 Station to Kolkata Airport (Biman Bandar).

This section of the 32 km Line-6 (Kavi Subhash New Garia – Netaji Subhash Chandra Bose International Airport) was originally envisioned to be underground, but large-scale land acquisition for its ramp and station at Teghoria (named Rabindra Tirtha) forced Rail Vikas Nigam Ltd. (RVNL) to convert a large potion of it – barring an approximate 950m airport stretch – into an elevated line.

RVNL invited bids for this package in June with an estimated value of Rs. 526.62 crore and expects the assigned contractor to complete all work within 36 months. Technical bids were opened in August to reveal 4 bidders.

Financial Bid Values:

FirmBid
Afcons InfraRs. 532.65 crore
ITD CementationRs. 552.85 crore
STS – KEC JVRs. 629.33 crore
GulermakRs. 688.09 crore

Contract / IFB No: RVNL/KOL/New Garia-Airport/Metro/ANVS

Scope: Construction of viaduct, ramp & underground RCC box (cut & cover, box pushing) including related works for 3.520 km length from CH. 25891.527 to CH28410.989 between existing Pier CP-760 (near City Centre II) to merging point with metro railway at Biman Bandar Station yard including two stations (Rabindra Tirtha & VIP Road) with all allied works (architectural, electrical, mechanical, heating, ventilation, air condition, fire detection, fire suppression, system & public health engineering works) in New Garia – Biman Bandar metro corridor of Kolkata Metro Railway Line, West Bengal

This package includes the construction of 2 stations at Rabindra Tirtha and VIP Road –

Indicative location of stations and route of Sub CBD-2 – Airport section – view Kolkata Metro info & route map

Afcons’ lowest bid of Rs. 532.65 crore was just Rs 6.03 crore higher than RVNL’s estimate of 526.62 crore, and shouldn’t be a deal breaker at all. If no extraneous issues arise during financial bid evaluation, then Afcons should be awarded with Line-6’s final major civil contract in the coming weeks with a 36 month deadline.

When awarded, if I’m not mistaken, this will be Afcons’ first major civil contract in Kolkata since 2010 when it won the 16.34 km east-west Line-2’s Package UG-01 (Howrah Maidan – Esplanade) with a contract value of Rs. 938 crore.

Update: Turns out Afcons had 2 civil contracts on Line-6 as well. This includes Package ANV1 with a 5.75 km viaduct between New Garia and VIP Bazaar and Package ANV3 with a 5.16 km viaduct between NICCO Park and CBD-1.

Coming back to Line-6’s airport section – back in May, RVNL had invited bids to appoint a Detailed Design Consultant (DDC), and the tender notice for that gives an idea about this civil package’s sub-sections. If anyone knows the winner for this contract, please drop a comment below or shoot me a message via the contact page.

  • Viaduct (2 sections)
    Section 1: (CH: 25900 approx.) to CP:801 (CH:27200 approx.)
    Length: 1300M (Approx.)
    Section 2: CP: 801 (CH: 27200 approx.) to start of ramp (CH:28450 approx)
    Length: 1250M (approx.)
  • Ramp/Underground
    Start of Ramp (CH:28450) to end of Design Limit (CH: 29400)
    Length: 950M (approx.)

For more updates, check out the Kolkata section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

14 Responses to "Afcons Wins Kolkata Metro Line-6 Airport Section’s Work"

  1. Manoj Sharma says:

    Congrats to team AFCONS

    Reply
  2. Anonymous says:

    Any update on green line southern extension (Bangalore)?
    Will it open on/by Jan 26?

    Reply
  3. Rupraj Sengupta says:

    Afcons had the viaduct contract from Kavi subash to VIP bazaar on line 6, seven stations were by its!

    Reply
  4. Rupraj Sengupta says:

    *itd

    Reply
  5. U says:

    TMRG what about Kolkata Metro line 3’s underground section general consultant bids??
    What is the status of viaduct construction on line 3,4,6??

    Reply
    • TMRG says:

      Results of L-3’s GC tender are awaited. Will share whenever declared and I hear something 🙂

      I don’t have a detailed updated, but briefly put – viaduct of 3, 4, 6 are ready in bits and pieces. Lines are 2+ years away from becoming operational due to a combination of encroachments + slow work (inefficiencies).

      Reply
  6. Gautam Sengupta says:

    Very good news for people of kolkata. But delay make it’s utility more cumbersome some as if a father telling his sons don’t worry your grandsons will be happy with as he may avail running of Metro to Garia from airport. His son is reading at school aged 12years

    Reply
  7. Hemendra kumar says:

    Congratulations Afcons

    Reply
  8. JAVED ALI ANSARI says:

    Congratulations to Afcons the most trusted Brand from the clan of Tata’s

    Reply
  9. Rajkumar Gowala says:

    Congratulations Afcons …… Kolkata work.
    Gantry crane operator job please check

    Reply
  10. D K Kunar says:

    Congratulations AFCONS. I have worked in Infra Projects for 50 years from 2013 till Jan 2014 and had interactions with some other company’s of Infrastructures and I find AFCONS is the best for Clients and Employees as well and following Govt. Rules. No Short Cut. Very ethical . Excellent Company for challenging Projects. It’s SP Group Company.

    Reply
  11. Arindam Ghosh says:

    Is any new Metro line open now, comparatively to other state WB has lesser in lengths.

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to D K Kunar Cancel reply

Your email address will not be published. Required fields are marked *