L&T & J Kumar Win Delhi Metro Silver Line’s Underground Work

Larsen & Toubro & J Kumar Infraprojects on Thursday emerged as the lowest bidders for constructing 2 underground tunneling packages (DC-09 & DC-08) of the 65.1 km Delhi Metro Phase 4 project‘s 23.622 km Silver Line.

Afcons Infrastructure and Tata Projects Ltd. (TPL) had originally won both civil contracts in November-December 2021. However, since their bids were significantly higher than the Delhi Metro Rail Corporation (DMRC)’s estimates, all qualified bidders were requested to submit revised financial bids.

Both packages come with a 42 month deadline and are being financed by JICA through a Rs 8,390 crore ODA loan.

Package DC-08

This 6.116 km Aerocity – Kishangarh section is on the western-end of the 23.622 km Silver Line and comprises of 4 stations at Aerocity, Mahipalpur, Vasant Kunj and Kishangarh.

  • Original Winner: Tata Projects Ltd. (TPL)
  • DMRC’s Estimate: 1349 crore

Financial Bid Results

FirmBid (Rs. Crore)
J Kumar Infraprojects1611.85
Tata Projects1639.02
L&T1684.35
Afcons1854.99
ITD Cem1926.29
Gulermak2237.64

Brief Scope: Design and Construction of Twin Tunnel (Up & Down Line) by Shield TBM, Cut and Cover Tunnel box and four Underground stations namely Aerocity, Mahipalpur, Vasant Kunj and Kishangarh with Entry/Exits & Connecting subways from chainage (-) 760 mt. to 5356.285 mt. of Aerocity to Tughlakabad Corridor of Phase-IV of Delhi MRTS.

Indicative alignment of Delhi Metro Silver Line’s Package DC-08 – view Phase 4 route map & info

DC-08’s design details such as crossover locations, TBM launching shafts and Aerocity Station’s design, in relation to the upcoming Delhi – Alwar RRTS Line, can be viewed here.

Package DC-09

This 6.51 km section, with twin-tunnels smack-dab in the middle of the Silver Line will connect Kishangarh Station’s east-end (chainage 5356.285) with a ramp (chainage 11867.000) west of Saket G Block Station through 4 stations at Chhattarpur (interchange with Yellow Line), Chhattarpur Mandir, IGNOU and Neb Sarai.

  • Original Winner: Afcons Infrastructure
  • DMRC’s Estimate: 1428 crore

Financial Bid Results

FirmBid (Rs. Crore)
L&T1737.22
Afcons1739.64
Gulermak1940.90
ITD Cem2028.40

Brief Scope: Design and Construction of Twin Tunnel (Up & Down Line) by Shield TBM, Cut and Cover Tunnel box, Underground Ramp and four Underground stations namely Chhattarpur, Chhattarpur Mandir, IGNOU and Neb Sarai with Entry/Exits & Connecting subways from chainage 5356.285 mtr. to 11867.000 mtr. of Aerocity to Tughlakabad Corridor of Phase-IV of Delhi MRTS.

Alignment of Delhi Metro Silver Line’s Package DC-09 – view Phase 4 route map with all stations’ exact locations marked

DC-09’s design details such as crossover and ramp locations can be viewed here.

J Kumar and L&T’s bids were 19% and 22% higher than DMRC’s estimates, so I don’t see contracts getting awarded anytime soon. DMRC will likely invite both firm’s management for negotiations, and if those fail, then we’ll likely see both going into a re-tender. Interesting times ahead.

With this development, here’s the status of all 4 JICA-funded underground packages of Phase 4.

Civil PackageStatus
Package DC-05: Derawal Nagar to RK Ashram, 7.46 km underground section with 6 stationsAwarded to Afcons Infra
Package DC-08: Aerocity to Kishangarh, 6.11 km underground section with 4 stationsJ Kumar is lowest bidder
Package DC-09: Kishangarh to Saket G-Block, 6.88 km underground section with 4 stationsL&T is lowest bidder
Package DC-07: Sangam Vihar to Tughlakabad, 6.477 km underground section with 3 stationsAwarded to Afcons Infra

See a list of all Delhi Metro Phase 4 packages and their status here.

For more updates, check out the Delhi Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

19 Responses to "L&T & J Kumar Win Delhi Metro Silver Line’s Underground Work"

  1. Shailesh says:

    When did DMRC reinvite tenders?

    Reply
  2. Jimmy Vij says:

    Hey TMRG, It’s been more than 2 years since elevated portion was awarded to YFC. Since then very few updates are there from that package. Is everything alright there ?

    Reply
    • TMRG says:

      Hi, operations on elevated section depend on DC-07’s tunnels leading to Sarita Vihar Depot. This is unconfirmed, but I believe DMRC has relaxed contract terms to minimize on-ground construction activity.

      Reply
  3. Joyanta Dey says:

    Last time in DC-08 J Kumar’s bid value was 1859.0 Cr now 1611.85 Cr and in DC-09 L&T’s bid value was 2610.0 Cr now 1737.22 Cr. How they can rebate like this ?

    Reply
    • TMRG says:

      Chennareddy explained it nicely below.

      On a different note, I don’t think DMRC changed the scope at all otherwise they would have re-invited fresh tenders.

      Reply
  4. Chennareddy Indla says:

    There are many factors to reduce the Quoted rates .
    1. They might have felt the work is in Delhi i.e capital city and the project after completion becomes a feathers in their cap.
    Second they might have thought with much profit,
    Thirdly they know they are very near to win hence moved a little.
    Fourth their machinary utalisation etc.

    Reply
  5. SANT KUMAR says:

    Job requirements

    Reply
  6. Nilarghya says:

    hi TMRG, do you know where can we find LnT and J kumar office and sites for this project?

    Reply
  7. RAVI VERMA says:

    Hi, can you please give name of companies who are working on DMRC’s phase IV projects ? regards

    Reply
  8. Yashwant sharma says:

    Civil supervisor experience 2years

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *