4 Bidders for Chennai Metro Line 5’s Track Work Contract

4 firms have submitted bids to supply and install standard gauge tracks for Chennai Metro’s Line-5 after Chennai Metro Rail Ltd (CMRL) opened technical bids for Package C-5-CP18B-ATW-12 on Saturday.

This new 47 km primarily-elevated corridor of the 118.9 km Chennai Metro Phase 2 project will run in a north-south orientation to connect Madhavaram – Sholinganallur via 48 stations.

This tender’s scope includes track-work between Madhavaram Milk Colony and CMBT Station and inside Madhavaram Depot. Back in April, Larsen & Toubro emerged as the lowest bidder for the line’s CMBT – Sholinganallur section.

CMRL invited tenders for this systems contract, financed by JICA, in January 2022 with a Rs. 194 crore estimate and 1006 day deadline + 730 day (DLP).

Bidders

  • KEC International Ltd.
  • Larsen & Toubro Ltd. (L&T)
  • Rail Vikas Nigam Ltd. (RVNL)
  • Texmaco Rail and Engineering Ltd.

Tender: Phase-II/C-5-CP18B-ATW-12/2022

Brief Scope: Supply, Installation, Testing and Commissioning of Ballastless Track of Standard Gauge including all associated works in Underground, Elevated and Madhavaram Depot of Chennai Metro Rail Project – Phase II Between CMBT to Madhavaram Milk Colony of Corridor 5.

Representational image only– Photo Copyright: Daily Mail

All bids have now been sent for technical bid evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely supplier.

As I mentioned in another post – things on the tendering side – both civil & systems – are moving along nicely although with some hiccups along the way for its rolling stock. This week CMRL plans to open technical bids for Line-3’s track-work and Line-4’s E&M contract.

A list of all Chennai Metro Phase 2 civil & system packages and their status can be viewed here.

For more updates, check out the Chennai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

4 Responses to "4 Bidders for Chennai Metro Line 5’s Track Work Contract"

  1. dsdfs sdfdsf says:

    how to know were exactly stations will be coming? is there any document, diagram available publicly for station locations?

    Reply
  2. Ram says:

    Still not tender for Line-5: Package UG-6 ?

    Reply
    • TMRG says:

      Re-tender notice was published in December. Bidding is underway. Current technical bid opening date is July 28.