Bids for Bangalore Metro Airport Depot’s Civil Work Invited
Bangalore Metro Rail Corporation Limited (BMRCL) this week invited tenders for the civil construction work of Bangalore Metro Blue Line’s Airport Depot.
This small train maintenance depot in Phase 2B (Airport Line) will serve the city’s new 57 km Blue Line, which along with Phase 2A (ORR Line), will connect Central Silk Board – KR Puram – Bengaluru International Airport.
The depot is also referred to as Doddajala Depot or Shettigere Depot. Per BMRCL’s August newsletter, a preliminary notice for acquiring an additional area of 12,576.619 sqm has been sent to the the government for approval.
This contract is being financed by the Asian Development Bank (ADB) which approved a USD 500 million (approx. Rs 3680 crore) loan in December 2020.
- Estimated Cost: Rs. 204.68 crore
- Deadline / Period of Work: 548 Days
- Pre-bid Meeting: 30 September, 2022 at 11:30AM
- Bid Submission Start Date: 21 October, 2022
- Bid Submission End Date: 29 October, 2022
- Technical Bid Opening Date: 31 October, 2022
Brief Scope: Construction of Airport Depot for Bangalore Metro Rail Project-Phase-2B
Operations on the Blue Line will also be supported by the Purple Line’s operational Baiyappanahalli Depot which will be converted in a phased manner to serve the Blue Line in the future. Bids for its reconstruction / remodel were invited in August.
Back in September 2021, PADECO Co. Ltd. – Ardanuy India Pvt Ltd. JV was awarded both depots’ Detailed Design Consultant (DDC) contract valued at Rs. 3.94 crore.
As shared earlier – both depots will house 222 new coaches (37 x 6) as part of a 318 coach contract financed by the Japan International Cooperation Agency (JICA). A tender notice for their procurement is still pending, which is fine for the Blue Line but now terribly delays the start of operations on Phase 2 project’s 21.38 km Pink Line till at least 2025.
For more updates, check out the Bangalore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
whats the update on the purple line whitefield extension??
Easily seems to be as TMRG previously said multiple times, mid 2023.
Great to see work on the blue line chugging along as it should. I’m expecting operations to start by 2028, owing to how AFCONS still hasn’t completed a majority of its piers and is easily 6 months behind schedule, unlike SNC or NCC. The yellow line also seems to be doing fine, although there’s little to no info regarding its CRRC rolling stock (again, why on earth did they choose a Chinese company, when BEML is literally right here?!)
And the pink line, well, it’s just sad. The tunneling is progressing somewhat steadily, but the viaduct for the elevated sections is barely there, and I don’t really see lots of progress with its segments. Hope it gets done by 2025 like you’ve predicted.
2028 is a very pessimistic timeline. The construction is using precast. Also there is very good progress on the entire stretch. Even from the airport to hebbal. It is believed to be the fastest completion metro line in Bangalore.
There seems to be no budget or spine, to complete the existing projects on time, not sure why new projects are being rolled out.
We are already suffering because of incomplete projects and request the concerned to address the existing issues before common man completely looses faith in democracy.
So, has the remaining 5 acres in Shettigere/Doddajala been acquired ??
Not yet
Then why inviting bids before land acquisition??
Pls update on Whitefield section, I see many stations work is pending and trial run is not yet started. This also may take one more year.
You’re right. Will open no sooner than mid-2023.
Padeco is real fraud company. Keep your hands off it.
Tell me more about it. Curious.
Any further plans to acquire properties around Nagawara station?
I would like to know when Silk board to Bommasandra Metro will be operational please
My guesstimate would be 18 months, for the complete yellow line, boss. Based on the track laying work that is pending.
Who told track laying works are pending? Tracks were layed almost everywhere this January itself. Even many stations are almost done, with traces of escalators and ticket counter chambers. Saw them while going to Madurai in a Night Bus on 4th Oct..
need list of Contractors & value