Mumbai Metro Line-6’s Station Finishing Contracts Awarded for 13 Stations
Mumbai Metropolitan Region Development Authority (MMRDA) in January awarded 3 contracts for architectural finishing work at 13 elevated stations of Mumbai Metro’s 15.18 km Line-6 (Pink Line) which will connect Swami Samarth Nagar (Lokhandwala) and Vikhroli.
These 3 contracts for packages CA-264, CA-265 and CA-266 also includes installation of pre-engineered building (PEB) roof and general site development works in the vicinity of the station area.
- Package CA-264: Awarded to SS SS Constructions (Rs. 76.68 cr) for 3 elevated stations between IIT Powai – Vikhroli EEH under construction by J Kumar Infraprojects (BC-01R1)
- Package CA-265: Awarded to NA Construction (Rs. 124.41 cr) for 5 elevated stations between Mahakali Caves – Powai Lake under construction by MBZ – EIIL JV (BC-02R)
- Package CA-266: Awarded to Landmark – Neev JV (Rs. 165.93 cr) for 5 elevated stations between Swami Samarth Nagar – Shyam Nagar under construction by J Kumar – CRTG JV (BC-03)
Bids for these long-delayed contracts were originally invited by Delhi Metro Rail Corporation (DMRC) in August 2023 under packages BC-04, BC-05 & BC-06. Those tenders were cancelled and re-invited by MMRDA in August 2024. Technical and financial bids were opened in September 2024.
Each contract comes with a 24 month deadline and a ‘Notice to Proceed’ start date of February 1, 2025.
Package CA-264
MMRDA’s Brief Scope: Architectural finishing works including design, fabrication, supply, erection & roof sheeting of Pre-Engineered Building (PEB) structures and design & construction of external facade, water supply, sanitary installation, drainage, site development works at Three (03) Elevated Stations namely IIT Powai, Kanjur Marg (W) and Vikhroli (EEH) of Mumbai Metro Line-6 Project.

Package CA-265
MMRDA’s Brief Scope: Architectural finishing works including design, fabrication, supply, erection & roof sheeting of Pre-Engineered Building (PEB) structures and design & construction of external facade, water supply, sanitary installation, drainage, site development works at Five (05) Elevated Stations namely Maha Kali Caves, SEEPZ Village, Saki Vihar Road, Rambaug & Powai Lake of Line-6, Swami Samarth Nagar to Vikhroli (EEH) corridor of Mumbai Metro Project.

Package CA-266
MMRDA’s Brief Scope: Architectural finishing works including design, fabrication, supply, erection & roof sheeting of Pre-Engineered Building (PEB) structures and design & construction of external facade, water supply, sanitary installation, drainage, site development works at Five (05) Elevated Stations namely Swami Samarth Nagar, Adarsh Nagar, Jogeshwari (W), JVLR & Shyam Nagar of Mumbai Metro Line-06 Project.

Here’s a cool drone view of Line-6’s viaduct shot in November by Kyle D’ Souza on YouTube showing the progress made on the civil structure:
MMRDA had re-invited bids for Line-6’s 108 coach rolling stock & signaling contract (Package CA-232) in February 2024. Looking at the current progress and pending procurement of critical systems, at this point I see Mumbai’s Pink Line opening for commercial operations no sooner than Q4 2027. This is a shame since civil contracts were awarded way back in 2018-19, similar to 35.2 km Line-4/4A (Green Line) which is also dragging.
For more updates, check out the Mumbai Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
H/T: Aryan Bagade
Hey TMRG!
Any progress on the metro line 9?
Haven’t heard anything about it since august.
Hi, track and electrification work is ongoing, we should see it open in Q4 or Q1 2027
The work of Metro6 is one of the longest.
Now this finishing contract will take another 24 months.
Never ending projects. 10 years and still less than 50% complete.
Hey, TMRG
What is the status of the METRO CAR DEPOT at Kanjurmarg for Metro 6? I hope it starts soon ASAP. without it, line 6 cannot run.
Still stuck in state vs central govt dispute
https://www.google.com/amp/s/www.moneycontrol.com/news/business/markets/datamatics-shares-rise-over-7-as-firm-signs-contract-for-pune-metro-line-3-12931261.html/amp
Pune Metro Line 3 AFC Contract awarded @TMRG.
Cool, thanks! Have updated Line-3’s info page: https://themetrorailguy.com/pune-metro-line-3-project-information-route-map-fares-tenders-updates/
That’s nice! 🙂