J Kumar’s Mumbai Metro TBM Disha Records Breakthrough for Line-7A
J Kumar Infraprojects (JKIL) on Thursday celebrated tunnel boring machine (TBM) Disha’s first and only breakthrough at the Airport Colony Shaft for Mumbai Metro Red Line’s 3.17 km Line-7A (Gundavali – CSIA).
TBM Disha (T62) of Package CA-48 is a Ø6.68m dual-mode Terratec machine that was previously deployed by JKumar – CRTG JV in 2018-2021 as Tapi-2 to build 3 tunnels for Package UGC-06 of the 33.5 km Line-3 (Aqua Line).
Following its final breakthrough at the Domestic Airport Station in February 2021, T62 was dismantled, transported and refurbished at J Kumar’s casting yard in Chenna village on Ghodbunder Road.
The machine, renamed as Disha, was launched in September 2023 from Chhatrapati Shivaji Maharaj International Airport (CSMIA)’s Terminal 2 Station and built a 1.647 km tunnel towards Airport Colony Ramp for Line-7A’s down-line.

Along the way, TBM Disha passed passed above Line-3’s twin tunnels and beneath the Sahar Elevated Access Road (SEAR) and utilities.

Mumbai Metropolitan Region Development Authority (MMRDA) had awarded J Kumar Infraprojects with Package CA-48’s Rs. 1,998 crore contract in September 2019.
J Kumar’s scope of work, besides the 11.38 km elevated Line-9 extension, includes building Line-7A’s viaduct, ramp, underground tunnels and 2 stations at Airport Colony and CSIA Terminal 2 where it’ll meet operational Line-3 (Aqua Line), and in the future Line-8 (Gold Line) linking to Navi Mumbai International Airport.



A video of the breakthrough can be viewed here on X.
TBM T60 (Dhruv) for the parallel up-line tunnel was launched a few months after Disha in November 2023 and is expected to arrive at Airport Colony’s Shaft in June. I hear less than 100 rings are left to be built.
At this time I see Line-7A becoming operational no sooner than mid-2027 looking at the standard system installation and station development work required to make a line operational in Mumbai.
For more updates, check out the Mumbai Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
1) Track work awarded for 7A?
2) 2B trial started till Diamond Garden
3) Line 12 some pillars made ready at Amandoot & Manpada.
Hey TMRG,
This would surely interest you- India’s longest rail tunnel completed in Uttarakhand
https://www.deccanherald.com/india/uttarakhand/indias-longest-rail-tunnel-completed-in-uttarakhand-3500682
PS- was recently travelling in the area and saw the series of tunnels and rail bridges being constructed along the entire stretch.