KEC Wins Patna Metro’s Electrification Work PE-01
October 12 Update: LOA contract to KEC has been issued with a value of Rs. 92,22,10,619.85 (Rs. 92.22 crore).
July 29 Original Post:
KEC International on Wednesday emerged as the lowest bidder for the RSS, TSS & ASS substation and cabling works of Patna Metro’s Phase 1 project after DMRC opened financial bids.
This is Patna’s very first electrification-work related package of the 30.91 km Phase 1 which will feature two mostly-elevated lines with 24 stations including 2 interchanges at Khemni Chak and Patna Junction Railway Station.
DMRC invited bids for this package in September with an estimate of Rs 104.22 crore and completion period of 36 months (3 years). Technical bids were opened in November to reveal 6 bidders out of which Linxon, Sterling & Wilson and Kanohar Electricals were disqualified during evaluation.
Financial Bid Values:
Firm | Bid (Rs. Crore) |
KEC International | 82.34 |
Siemens | 94.99 |
Kanti Prashad Mittal | 95.31 |
Contract: PE-01
Scope: Design, Supply, Installation, Testing and Commissioning of Receiving cum Traction (RSS + TSS) and Auxiliary Main Substation (ASS) including High Voltage Cabling from Grid Substation for Patna Metro Rail Project.
KEC’s bid of 82.34 crore was well below DMRC & PMRC’s budgeted estimate of Rs 104.22 crore, so a contract should be awarded in the coming weeks without much fuss.
This will be KEC’s second win in Patna Metro’s Phase 1. Back on July 16, they were also the lowest bidder for New ISBT Depot’s ballasted track-work contract (PT-08).
With this development, 3 more ongoing tenders are waiting for their financial bids to be opened. This includes track-work tenders Package PT-07 & Package PT-04 and E&M package Package PE-02. Stay tuned…
For more updates, check out the Patna section or my Home Page!
– TMRG
Patna metro is going in for ohe or third rail power supply?
OHE
Thank you for the information!
Hi TMRG,
MoHUA has uploaded this press release on the PIB site showing the status of all Metro projects under construction and the proposals recieved for approval.
https://pib.gov.in/PressReleasePage.aspx?PRID=1740315
Cool!
Any update on missing link of DMRC pink line. When it will be inaugurated.
Aug 6 – as you might have heard by now
Do you have the confirmation of CMRS inspection dates for Kengeri extn. now?
Sources said, that it will be conduct by 11th and 12th August
Hearing 10-12
https://twitter.com/urbantransnews/status/14213199591629998784?s=20
Construction started for underground stretch in Chennai metro’s phase 2?
Need to check if piling has started. Likely hasn’t.
Dost, Olympic follow karne mein busy ho lag raha hai….
lol 🙂
Wrapping up an important milestone – need a couple days.
Ok. Take your time mate..
Ohe
ITI tred electrician and maintenance pls job me argent call 7646004981 in patna bihar