Bangalore Metro’s TBM Varada Makes 2nd Breakthrough at Langford
Tunnel Boring Machine S-1264 operated by Afcons Infrastructure last week recorded a tunnel breakthrough at Langford Town Station for Bangalore Metro’s 21.386 km Pink Line (Nagawara – Kalena Agrahara).
Nicknamed Varada, this was TBM S-1264’s second and final breakthrough for 3.655 km Package RT-01 (Rashtriya Military School Station – Dairy Circle Ramp) of the 73.92 km Bangalore Metro Phase 2 project.
This refurbished Herrenknecht earth pressure balance (EPB) machine was originally commissioned in March 2021 from Rashtriya Military School Station (near Vellara Junction) to build the 596 m up-line tunnel towards Langford Town where it recorded a breakthrough in November 2021.
The machine’s parts were then brought back to RMS Station and relaunched in January 2022 to build the parallel 596m down-line tunnel.
Images via BMRCL:
Per the tunneling plan, Afcons was hoping to complete tunneling on this section in 235 days, and they accomplished the task in 225 days.
A video can be viewed here posted by Christin Mathew Philip at TOI.
BMRCL’s recent August newsletter indicates approximately 57% of tunneling work has been completed for Phase 2 (total scope: 20,855m).
With this development, TBM Varada’s job for the project is over and will now be retired. A total of 13 out of 26 breakthroughs have recorded: 4 on Package RT-01 by Afcons, 2 on RT-02 by L&T, 4 on RT-03 by L&T, and 3 on RT-04 by ITD Cementation.
For more updates, check out the Bangalore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.
– TMRG
How many breakthroughs left in package 1?
4 more
When pink line will be ready for commutation to public
Another 4 nos. 2 at Lakkasandra Station and 2 at Langford Town Station.
Hi TMRG,
The last segment for the RV Road to HSR Layout double decker was viaduct was lifted last week near Jayadeva Station.
https://twitter.com/Manava_Dharma/status/1568580966729527297
With this one more milestone of the yellow line is completed.
Thanks, I’m aware! Significant milestone. Might write a quick post.
Update. Posted here: https://themetrorailguy.com/2022/09/17/hcc-urcc-launches-bangalore-metro-yellow-lines-final-segment/
Hi TMRG
When pink line will ready for commutation to public?
Rt02 going to crack middle of this month
We did it today