Afcons Casts Ahmedabad Metro Phase 2 C1’s 1st Pile Cap
Workers from Afcons Infrastructure on Monday night poured concrete to cast their…
Workers from Afcons Infrastructure on Monday night poured concrete to cast their…
Here we go once again. Noida Metro Rail Corporation (NMRC) on Monday re-invited…
Alstom Transport India has in the past fortnight began installing anchor bolts…
Linxon India in mid-May began installing the 750 V Third Rail electrification…
Afcons Infrastructure this past week began work for a 550 meter bridge over…
HCC – KEC JV (Hindustan Construction Company Ltd. – KEC International Consortium)…
Besides the start of trial runs on Line-2A and Line-7, another signficant milestone…
Maha Mumbai Metro Operation Corporation Ltd. (MMMOCL) today officially started…
Gulermak – Sam India Builtwell JV has in the past fortnight started ground work to setup a casting yard in Kanpur’s Makdikhera neighborhood to…
Workers from Ranjit Buildcon Ltd. on Friday began pouring concrete to cast pier caps for Ahmedabad Metro’s 28.254 km Phase 2 project at their…
Sam India Builtwell – Gulermak JV on Wednesday evening erected their first U-girder to construct the elevated viaduct for a 7.473 km extension of Delhi…
Mumbai’s depot issues just don’t seem to end. Mumbai Metropolitan Region Development Authority (MMRDA) has in the past week cancelled the tendering…
ITD Cementation India on Wednesday started lowering parts of Tunnel Boring Machine Bhadra (S-840B) at Venkateshpura Station on Bangalore Metro’s 21.386…
J Kumar Infraprojects today finally received a Letter of Acceptance (work order) for completing pending (balance) construction work on the DN Nagar –…