L&T’s Pakal Dul HEP TBM Marsu Assembled in J&K
Larsen & Toubro on Sunday completed assembly work on Herrenknecht tunnel…
Larsen & Toubro on Sunday completed assembly work on Herrenknecht tunnel…
Larsen & Toubro today lowered DZ1091 – their 2nd of four tunnel boring…
Shanghai Tunnel Engineering Co. Ltd. (STEC) today celebrated tunnel boring machine…
Tunnel boring machine manufacturer Terratec on Friday completed factory acceptance…
September 26, 2023 Update: MMRDA has awarded a contract to SEW – VSE JV for…
Larsen & Toubro today commissioned DZ1090 – the 1st of four tunnel boring…
IRCON International – Dineshchandra R. Agrawal Infracon JV this Monday launched…
Siemens Ltd. – Rail Vikas Nigam Ltd. JV on Thursday was declared as the…
Five firms on Wednesday submitted bids to supply and install ballastless tracks on a 12.72 km section of Mumbai Metro Orange Line (Line-5) which will connect…
June 8, 2023 Update: Afcons and NHSRCL have signed a Rs. Rs. 6397.27 crore contract for the civil construction of Package C2. LOA was issued in mid-May….
Larsen & Toubro last week celebrated casting the final of 5593 box segments for 82.15 km Delhi – Meerut RRTS project’s 15.84 km Package 3 Lot-1…
Ranjit Buildcon Ltd. (RBL) this Saturday poured concrete to cast their first pier for 4.15 km Sarthana – North Ramp (Package CS4) of the 41.93 km Surat…
J Kumar Infraprojects last week commissioned Terratec tunnel boring machine S28B at Surat Railway Station for Surat Metro Phase 1 project’s 3.56…
Another contract down! Larsen & Toubro last week was awarded the telecommunication contract (Package ASA05) for Chennai Metro’s 26.09 km Line-4 which…