TBM S64 Makes Final Breakthrough for Mumbai Metro Line-3’s UGC-05

Moments ago, Tunnel Boring Machine (TBM) S64 operated by the J Kumar Infraprojects – China Railway Tunnel Group JV made a breakthrough at Dharavi Station’s northern-end on Mumbai Metro’s 33.5 km Aqua Line (Line-3).

This was S64’s second (and final) breakthrough, J Kumar – CRTG’s sixth (and final) breakthough for the 4.94 km Dharavi – CSIA T1 package UGC-05, and overall Mumbai Metro Line-3’s 30th TBM breakthrough.

Like its sister machine S63 (Godavari-3), this Ø6.61m Terratec Earth Pressure Balance TBM, nicknamed Godavari-4, previously saw action in Delhi to build its new Pink Line (package CC-20 / CC-24) for the 162 km Phase 3 project, and was then extensively refurbished and retooled for this section’s highly weathered ground conditions at a yard located in Mundka, Delhi.

The TBM was first commissioned from BKC Station’s northern-end in October 2018 to build the 886 meter up-line tunnel to Vidyanagari Station. After its breakthrough in April 2019, it was then recommissioned to build the 1462 meter up-line tunnel towards Dharavi Station during which it passed right beneath the Mithi River at a depth of 8-12m below the riverbed. 

Route of UGC-05 (Dharavi – CSIA Terminal 1) – view Mumbai Metro info & map
Photo Copyright: Suraephong Soo Jaitong

Last week, a TOI article quoting MMRCL suggested 45,560/54,523m (83%) of tunneling works had been completed.

With this development, tunneling works on 3 out of 7 packages have been wrapped up –

  • UGC-02: CST – Mumbai Central (4.049 km) – Final breakthrough recorded by TBM T59 (Vaitarna-2) in April 2020
  • UGC-05: Dharavi – CSIA T1 (4.94 km) – Final breakthrough recorded by TBM S64 (Godavari-4) today
  • UGC-07: CSIA T2 – Sariput Ramp (4.157 km) – Final breakthrough recorded by TBM D213 (Wainganga-2) in December 2019.

With 30 breakthroughs completed, there are now just 11 more breakthroughs pending (this table is best viewed on a desktop device)

PackageSectionDistance, Status
UGC-01Churchgate – Hutatma Chowk (up-line)660m, In Progress
UGC-01Hutatma Chowk – CST (up-line)551m, Not Started
UGC-01Churchgate – CST (down-line)1233m, In Progress
UGC-03Science Museum – Mahalaxmi (up-line)1118m, Not Started
UGC-03Mahalaxmi – Mumbai Central (up-line)837m, Not Started
UGC-03Science Museum – Mahalaxmi (down-line)1136m, Not Started
UGC-03Mahalaxmi – Mumbai Central (down-line)830m, Not Started
UGC-04Siddhivinayak – Dadar (up-line)1106m, In Progress
UGC-04Siddhivinayak – Dadar (down-line)1126m, In Progress
UGC-06Sahar Road – CSIA T1 (up-line)1516m, In Progress
UGC-06Sahar Road – CSIA T1 (down-line)1512m, In Progress

For more updates, check out the Mumbai section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

9 Responses to "TBM S64 Makes Final Breakthrough for Mumbai Metro Line-3’s UGC-05"

  1. Rupraj Sengupta says:

    Has the depot works started as yet?

    Reply
  2. Arun says:

    Congrats JK team

    Reply
  3. Kanishka says:

    Hi TMRG,

    Will it be practically possible to finish the tunneling works (i.e. achieve the remaining 11 breakthroughs) by the end of this year/31st Dec?

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to Rupraj Sengupta Cancel reply

Your email address will not be published. Required fields are marked *