Ahluwalia Wins Mumbai Metro Line-2B Mandale Depot’s Pending Work
November 9 Update: After negotiation, Ahluwalia Contracts has been awarded Mandale Depot’s Rs. 530.32 crore contract.
Original Post:
Ahluwalia Contracts (India) Ltd. today emerged as the lowest bidder for completing the pending (balance) work at Mandale Depot of Mumbai Metro’s 23.6 km Line-2B (Yellow Line), after officials from the Mumbai Metropolitan Region Development Authority (MMRDA) opened financial bids for Package C103 this afternoon.
The depot at Mandale will be the second maintenance depot (car shed) of the entire 42.2 km Line-2 and become the largest in Mumbai when built. Its development is crucial since the first depot at Malvani in Malad West will temporarily also have to service Line-7’s BEML trains.
Per the plan, Mandale Depot will have a double-decker structure to stable a maximum of 72 trains of 8-coaches (total 576), and will come along with staff quarters, 9 inspection bays and 15 workshop lines.
Its construction contract was originally awarded to RCC Infra Ventures Ltd. – MBZ JV in 2017 under package CA-14, but terminated in January 2020 due to poor progress.
MMRDA then invited tenders for its pending work in February 2020 with an estimate of Rs 464.75 crore and opened technical bids in July to reveal 6 bidders. During technical bid evaluation – bids from Capacite, Man Infra and Relcon Infra were found to be technically non-compliant to the tender conditions, so their bids were disqualified and financial bids were not opened.
Financial Bid Values:
Firm | Bid |
Ahluwalia Contracts (India) Ltd. | Rs. 543.28 crore |
NCC Ltd. | Rs. 554.91 crore |
Afcons Infrastructure Ltd. | Rs. 587.12 crore |
Capacite Infraprojects Ltd. | Disqualified |
Man Infraconstruction Ltd. | Disqualified |
Relcon Infraprojects Ltd. | Disqualified |
Package: L2B-C103
Brief Scope: Construction of (Balance Civil works of CA-14) Mandale Depot [including Architectural Finishing works and excluding Pre-Engineered Structure works] of Line 2B Corridor [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA
Although the lowest, Ahluwalia’s bid was still Rs. 78.53 crores (roughly 17%) higher than MMRDA’s estimate, so it remains to be seen if the MMRDA will (1) award as-is, (2) reduce the scope of work and negotiate to bring the final contract value down, or (3) totally scrap the bidding process and invite tenders again. The last two options will introduce further delays in its completion with number-2 being the one with the shorter duration. If and when awarded, Ahluwalia Contracts will have 42 months to complete all pending civil work.
For more updates, check out the Mumbai section of The Metro Rail Guy!
– TMRG
Now MMRDA, should awarded the contract to Ahluwalia Infroprojects to prevent any further delay even their bids are high. If they scrap the bidding process, then the line will loose public confidence and they will once again says, this line is doom. I hope MMRDA will do better decision this time
What happened to the previous contractor ?
Previously, the contract was awarded to RCC-MBZ JV in 2017, and guess what after 3 years of construction, only 6% of the overall Construction work has been complete, bcoz of this MMRDA have terminate a contract on Jan.
line 2B is cursed
When it’s the last date of submission of bids for the Yellow Line Phase 2 (Line2B) balance work? Did they also floated tender to construct 3 iconic Bridges?
Current submission date is 16th and opening on 19th. Scope is supposed to include iconic bridges, but the brief one-liner scope doesn’t mention anything on it.
Hello, Any updates in the list of bidders for ICONIC bridges of MMRDA for Mumbai Metro package C-106
That tender was canceled
Thank you. Any updates of bidder for MMRDA/MMRP/L2B-C101 & C 102
Current submission date is 16th and opening on 19th. I’ll share bidder names when I become aware.
Any further updates in bidder names.
Hi! Is there any update about the architectural finishing works contract for Delhi Metro Janakpuri W – RK Ashram line (DC-10 I suppose)?
Just one bidder. See – https://themetrorailguy.com/2020/10/07/dra-infracon-only-bidder-for-delhi-metros-package-dc-10/
when will metro 2b start running any deadline date
Civil all work
Civil all work 9936063784