DRA Infracon Only Bidder for Delhi Metro’s Package DC-10

Dineshchandra R. Agrawal Infracon Pvt. Ltd. on Tuesday emerged as the sole bidder to perform architectural finishing works and install prefabricated steel roof structures including foot-overbridges at 15 new elevated stations on Delhi Metro’s Magenta Line which is being extended in the Phase 4 project by 28.92 km from Janakpuri West to RK Ashram.

Civil work for these 15 stations is currently being carried out by CCECC – KEC JV for the 12.375 km Package DC-01 (Vikaspuri Ramp – Haiderpur-Badli Mor) and by Sam India – Gulermak JV for the 7.473 km Package DC-03R (Haiderpur Badli Mor – Ashok Vihar) sections.

Delhi Metro Rail Corporation (DMRC) had invited tenders (bids) for Package DC-10 in August 2020 with an estimated cost of Rs. 183.72 crore, and expects the assigned contractor to complete work in 24 months.

Scope: Architectural Finishing Works Including Design, Fabrication, Supply, Erection & Roof sheeting of Prefabricated Steel Roof Portal Pre- Engineered Building (PEB) Structures & Foot Over Bridge (FOB) including Design & Construction (Substructure & Superstructure) & necessary changes in existing station for connection of FOB, External facade, Water Supply, Sanitary Installation, Drainage, Site development works at Fifteen Elevated Stations on Janakpuri West to RK Ashram Corridor of Phase-IV of Delhi MRTS.

The 15 stations in this package are located at Keshopur, Paschim Vihar, Peeragarhi, Mangol Puri, West Enclave, Pushpanjali, Deepali Chowk, Madhuban Chowk, Prashant Vihar, North Pitampura, Haiderpur Badli Mor (over existing Line-2 station), Bhalaswa, Majlis Park, Azadpur & Ashok Vihar.

Route of Magenta Line between Keshopur and Ashok Vihar with key stations marked – view Delhi Metro Phase 4 info & route map

With just one bid received, I’m not sure what DMRC’s game plan is going to be. If they’re not satisfied with the response, then this round of bidding will be scrapped and head towards a re-tender. If they decide to go ahead in the interest of time, then DRA Infracon’s technical bid will be evaluated over the next couple months. If it meets the tender conditions, then DC-10’s contract will be awarded to DRA Infracon provided their financial bid is also within a certain range of the original estimate.

October 21 Update: DMRC has cancelled the tender with the following message:

The following tender has been discharged due to participation of lone bidder i.e. not enough participation. The financial bid of the above tenderer will not be opened. This is as per the approval of the competent authority.

Meanwhile, there’s still no word on when the final tender notice for this line’s underground section (Ashok Vihar Ramp – RK Ashram) will be published. Construction on that roughly 7 km Package DC-05 and the Silver Line’s underground section (Package DC-07, DC-08 & DC-09) are dependent on the Japan International Cooperation Agency (JICA)’s approval.

For more updates, check out the Delhi section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

12 Responses to "DRA Infracon Only Bidder for Delhi Metro’s Package DC-10"

  1. Clevin Gomes says:

    What about work between Vikaspuri Ramp to Haiderpur Badli Mor?. I heard that work was stopped due to lack of environmental clearance. Since then, there is no update about it. Can u please tell us about it

    Reply
    • TMRG says:

      The stretch from Vikaspuri – Najafgarh Drain – Peeragarhi (deemed as a ‘forest’) is affected, but work is underway elsewhere.

      Reply
  2. Sanjay panday says:

    sir i am sai Enterprises govt contractor all type of civil and mechanical work manpower labour supplier sir new delhi contact number sanjay panday 8700147975/9953135576

    Reply
  3. Priyesh says:

    does the JICA approval for underground sections usually takes this much time?
    Or are we missing a deadline here?
    I mean JICA really does not do this…

    Reply
    • TMRG says:

      You’re right – this delay is unprecedented. JICA started indicating around 2017 they’d be performing further scrutiny for Phase 4, so while I’m not surprised, I am a little disappointed with how things are panning out.

      Reply
  4. Gimmi says:

    Sir. What is the progress of rituals to narela line. Is it possible to routed through sector 5 where the biggest establishment in bawana ( 1500mw combined cycle power plant of Delhi government)

    Reply
    • TMRG says:

      Rithala-Narela line’s DPR is ready and needs Central Govt’s approval. There are plans to build it as a Metrolite line instead. Let’s see…

      Reply
  5. Pawan Rajput says:

    I am civil site engineer if have any vacancy of civil site engineer please contact me

    Reply
  6. Mohit says:

    Sir , Any idea anout progress on remaining lines (Inderlok to Indraprastha
    , Lajpat Nagar to Chattarpur , Kirti Nagar to Dwarka) of phase 4 , why these lines are not approved by central Govt yet ?

    Reply
  7. anil kumar sharma says:

    Served superstructures and workshops for dmrc.contact for project management
    9810281568

    Reply
  8. Amandeep Singh says:

    I am Civil engineer I have 5 years experience Railway & metro sir I need a job plz help me. Mob. Num. 7589152001
    Email – [email protected]

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to TMRG Cancel reply

Your email address will not be published. Required fields are marked *