STEC Awarded Delhi – Meerut RRTS Package 4’s Contract

Multiple industry sources have confirmed to me that Shanghai Tunnel Engineering Co. Ltd. (STEC) was late-last week finally awarded a Rs. 1126.89 crore contract to build the 5.6 km New Ashok Nagar – Sahibabad underground Package 4 of the 82.15 km Delhi – Meerut RRTS project.

Update: Contract to STEC was awarded on December 9, 2020.

This underground package’s twin tunnels, mostly within Delhi, will be built using at least 4 tunnel boring machines (TBMs) and connect the New Ashok Nagar Down Ramp with the Sahibabad UP Ramp through one station at Anand Vihar where the line will be connected to the Delhi Metro’s Blue and Pink lines for easy transfers.

National Capital Region Transport Corporation (NCRTC) had invited tenders for this package on November 11, 2019 and technical bids were opened on March 16 to reveal 5 bidders.

Financial bids were opened on June 12 to reveal STEC as the lowest bidder amidst the India – China border conflict which reached its apex on June 15. This put NCRTC and the Indian government between a rock and a hard place as STEC had qualified in the technical bidding stage.

Although the Government of India had amended its bidding policy for public projects in mid-July, the bidding process for Package 4 couldn’t be scrapped for retendering as it had followed the chief lender, Asian Development Bank (ADB)’s, procurement guidelines.

Here’s a look at the financial bids again where STEC beat L&T narrowly by just Rs. 43.11 crore

FirmBid
Shanghai Tunnel Engineering Co. Ltd. (STEC)Rs. 1126.89 crore
Larsen & Toubro Ltd. (L&T)Rs. 1170.00 crore
Gülermak Agir Sanayi Insaat ve Taahhut A.S. (Gulermak)Rs. 1325.92 crore
Tata Projects Ltd. – SK E&C JV (TPL – SKEC JV)Rs. 1346.29 crore
Afcons Infrastructure Ltd. (Afcons)Rs. 1400.40 crore

Contract Number: DM/CN/COR-OF/086

Brief Scope of Package 4: Design and construction of tunnels of Package 4 by Tunnel Boring Machine from near New Ashok Nagar DN Ramp to Sahibabad UP Ramp and for one underground station at Anand Vihar by cut & cover method [Including Architectural Finishing and Design, supply, installation, testing and commissioning of Electrical and Mechanical Systems including Fire detection & suppression Systems and Hydraulic systems].

Route of New Ashok Nagar DN Ramp – Sahibabad UP Ramp of Delhi – Meerut RRTS Line – view project info & full map

With this development, all civil packages on the main-line have been awarded by NCRTC. Here’s a list of all packages and their status:

Package / SectionStatus
Package 1: Sahibabad Ramp – Ghaziabad Station (elevated, approx. 7.3 km with 2 stations)Under construction by KEC-CCECC JV
Package 2: Ghaziabad Station – Duhai EPE crossing (elevated, approx. 10.3 km with 2 stations)Under construction by APCO-CRFG JV
Package 3 (2 Lots): Duhai (EPE) – Modi Nagar North –Shatabdi Nagar (elevated, approx. 33 km 9 stations)Under Construction by Larsen & Toubro
Package 4: New Ashok Nagar Ramp – Anand Vihar – Sahibabad Ramp (underground, approx 5.6 km with 1 station)Awarded to STEC (this post!)
Package 5A: Duhai Depot / WorkshopAwarded to VNC – KEC JV
Package 5B: Modipuram Depot / WorkshopTender Notice Pending
Package 6: Sarai Kale Khan – New Ashok Nagar (elevated, approx. 4.3 km with 2 stations)Awarded to Afcons Infrastructure
Package 7: Shatabdi Nagar – Brahampuri – Brahampuri DN Ramp (elevated, 1 station) AND Begumpul UP Ramp – MES Colony – Daurli – Meerut North – Modipuram (elevated, approx. 12 km with 4 stations)Awarded to Larsen & Toubro
Package 8: Brahampuri DN Ramp to Begumpul UP Ramp (underground, approx. 5.7 km with 3 stations)Awarded to Afcons Infrastructure

A list of all RRTS packages (civil & systems) and their status can be viewed here.

For more updates, check out the NCR RRTS section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

6 Responses to "STEC Awarded Delhi – Meerut RRTS Package 4’s Contract"

  1. Akshat says:

    I knew the government couldn’t do anything

    Reply
    • Himanshu Doria says:

      Timing matters my friend. NCRTC would risk getting blacklisted from ADB if they go back on the terms of loan agreement. It is what it is.

      Reply
      • TMRG says:

        Exactly. Canceling the process would have resulted in ADB possibly pulling out, leading to the entire project being put on-hold.

        Reply
  2. Himanshu Doria says:

    I am glad that the govt bit the bullet and went ahead with contract awarding. Self-reliance and preventing Chinese companies from capturing market is a good exercise but one should be pragmatic and should not be cutting off nose to spite the face.

    Ofcourse L&T would not mind losing this after getting two back-to-back mega contracts 😉

    Reply
  3. Nikky Gupta says:

    Is it true that NCRTC has again engaged with Chinese companies for AC in RRTS coaches for Delhi -Meerut RRTS

    https://economictimes.indiatimes.com/news/economy/infrastructure/rapid-rail-ac-order-to-china-firm-under-dpiit-scanner/articleshow/82952682.cms

    Reply
  4. Sumeet Jain says:

    Looking for architectural finishing engineers and other staff for delhi and mumbai. Contact 9873707045

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *