DDC Bids Invited for Bangalore Metro Phase 2A & 2B’s Depots

Bangalore Metro Rail Corporation Limited (BMRCL) today invited bids from engineering design firms for the appointment of a Detailed Design Consultant to assist with building Doddajala Depot and remodeling the existing Baiyappanahalli Depot.

Both depots will serve the city’s new 57 km Blue Line in the upcoming Phase 2A and Phase 2B project linking Central Silk Board – KR Puram – Airport. While Doddajala Depot adjacent to Phase 2B’s “Airport Line” will be entirely new, the existing Purple Line’s Baiyappanahalli Depot near Phase 2A’s “ORR Line” will be repurposed and augmented, as shared back in 2016.

Tender: BMRCL/Phase-2A&2B/Airport Depot & Byp Depot/DDC/2021/76

Brief Scope: Detailed Design Consultancy (DDC) for Airport Depot at Doddajala and Remodelling of existing Baiyappanahalli Depot for Bangalore Metro Rail Project- Phase-2A&2B.

  • Duration of Service: 36 months
  • Bid Submission Deadline: June 15, 2021 at 3 pm
  • Technical Bid Opening: June 15, 2021 at 3:30 pm
Location of both depots on Bangalore Metro’s new Blue Line – view detailed Phase 2A info and Phase 2B Info

The tender notice doesn’t give much details, but to give a little background – the existing Baiyappanahalli Depot was built by URC Constructions in Phase 1 and consists of 16 stabling bay lines (SBL), 3 inspection bay lines (IBL) and 4 repair bay lines (RBL). Its remodel in Phase 2A involves augmenting stabling capacity from 16 to 42 lines, with the possibility of new level getting added.

A new facility for maintaining Blue Line’s Communication Based Train Control (CBTC) equipped-trains at Baiyappanahalli is planned in a phased manner so that it doesn’t affect train operations on the Purple Line. When the Purple Line’s Kadugodi Depot and Challaghatta Depot go live, Baiyappanahalli Depot will be fully converted to service the Blue Line’s CBTC equipped trains only.

The Asian Development Bank (ADB) has in the past revealed that this remodeling work will be taken up only after Phase 2B’s Doddajala Depot is built. This work will be carried out in two phases:

In the first phase 12 stabling lines will be constructed and a combined shed with 4 inspection lines and 2 repair lines and pit wheel lathe PWL line by the year 2023. In the second phase, two more repair lines and test track of 750 m length shall be constructed. The balance O&M requirement for this section will be supplemented by the facility at Baiyappanahalli depot. Remodelling work of Baiyappanahalli Depot related to 2B, shall be taken up only after construction of Airport depot facility.

Both depots will house 222 new coaches (37 x 6) as part of an upcoming 318 coach contract financed by the Japan International Cooperation Agency (JICA). Tenders for both depot’s civil works will be invited after detailed designs are ready which I imagine would happen no sooner than mid-2022.

For more updates, check out my Home Page!

– TMRG

Hat-tip: @bengalurutrains on Twitter

written by

Global traveler who prefers mass rapid transit

10 Responses to "DDC Bids Invited for Bangalore Metro Phase 2A & 2B’s Depots"

  1. Hind says:

    Why do Purple Line and Green Line need a depot at either ends?

    Reply
    • TMRG says:

      Land is relatively cheaper and in larger sized lots outside the city.

      Green Line needs the one at Anjanapura to support new extensions. Purple Line needs two depots to support the existing route and new extensions.

      Reply
  2. Arjun says:

    Any idea when construction for the Silk Board KR Puram line will start?

    Reply
    • TMRG says:

      Couple months after work orders are issued for construction to Afcons & Shankarnarayana, which should happen anytime now

      Reply
  3. Ashok N says:

    What is the scope of work of the phase 2A contract with respect to Silk board junction? What is scope of work for the current yellow line contractor HCC – URC? Will HCC – URC just build a down ramp before the junction and leave it?

    Reply
  4. Shashi says:

    when will start the mysore road to kengeri metro

    Reply
    • TMRG says:

      Train testing as of now has come to a complete stop due to COVID.

      Line will open sometime towards the end of Q3 (Aug/Sept). Expect delays if things don’t get better.

      Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *