L&T Launches Chennai Metro Line 3’s 1st U-Girder on OMR
Larsen & Toubro (L&T) on Wednesday launched their first U-girder for constructing 45.4 km Chennai Metro Line-3’s 10 km elevated package EV-01/RT-01 between Nehru Nagar – Sholinganallur.
This major milestone of the 116.1 km Chennai Metro Phase 2 project was recorded between Okkiyampet and Karapakkam on Old Mahabalipuram Road (OMR) using a 30 meter long U-girder.
This is the longest ever U-girder to be erected in India for building a metro line’s viaduct. U-girders elsewhere, such as Delhi, Bangalore, Mumbai, Kanpur etc., have typically been a maximum of 27.90 meters long.
Per Chennai Metro Rail Ltd. (CMRL)’s press release, Larsen & Toubro deployed an innovative puller axle system for transporting and erecting the girder, a first in Indian metro rail construction.
This special fabricated trailer made solely for the OMR stretch with 12 axles each with 8 tyres totalling to 96 tyres meticulously distributed across two axles, the puller axle not only emphasizes CMRL’s unwavering commitment to excellence but also establishes a new benchmark in metro construction ensures optimal weight distribution, stability, and flexibility during the seamless transportation of the 185MT U Girder.
CMRL had awarded EV-01/RT-01’s Rs. 963 crore construction contract to L&T in June 2022 with a 36 month deadline. Casting works for U-girders started in February 2023.
L&T’s scope includes constructing a 10 km viaduct starting from a ramp south of Taramani Link Road Station with 9 stations at Nehru Nagar, Kandanchavadi Perungudi, Thoraipakkam, Mettukuppam, PTC Colony, Okkiyampet, Karapakkam, Okkiyam Thoraipakkam and Shalinganagallur.
Tunneling work north of the ramp is also being carried out by L&T as part of Package TU-02.
A video posted by CMRL can be viewed here on X.
L&T recorded this milestone in 19 months since the award of contract. This is on the higher side compared to U-girder launches elsewhere.
Site conditions vary vastly across the country, but for comparison with ongoing projects: JMC Projects took 7 months to launch their first U-girder in Kanpur, Sam India Builtwell took 13 months for Agra Metro, NCC took 17 months for Bangalore Metro’s Airport Line, while YFC Projects – Montecarlo JV took 21 months in Patna.
For more updates, check out the Chennai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
Congrats L&T🥳🥳🥳
Great work
Please make the OMR road free from traffic
I AM ALWAYS A FAN OF L & T ! CONGRATS!