Bangalore Metro – February 2017 Phase 1 Update
Over this weekend, the Bangalore Metro Rail Corporation Ltd. (BMRCL) made their…
Over this weekend, the Bangalore Metro Rail Corporation Ltd. (BMRCL) made their…
Late last month, workers from SP Singla Constructions Pvt Ltd. performed the…
The contractor for the last civil package of Ahmedabad Metro’s 39.259…
The recently constituted Maharashtra Metro Rail Corporation Ltd. (MahaMetro) has…
The Delhi Metro Rail Corporation has revised their publicly facing deadline…
If you’ve been following along, then this shouldn’t come as a surprise….
The Kochi Metro Rail Ltd. yesterday extended trial runs/testing to Aluva Station…
Following a small pooja and ceremony, workers from the Tata – Gülermak JV today…
On this past Friday, India’s Railway Minister Suresh Prabhu remotely flagged off Kolkata Metro’s 2nd refurbished train from its old non-AC fleet…
Two months after inviting bids from infrastructure companies for the construction of Reach 4’s 8.15 km viaduct, the Nagpur Metro Rail Corporation…
Yesterday afternoon, Tunnel Boring Machine S197 made a final breakthrough at Najafgarh to complete all tunneling works on the Delhi Metro’s 4.3…
Earlier this week, workers from Simplex Infrastructures removed formwork (casting molds) to finish casting their first pillar in Goregaon East for Mumbai…
Hat tip to reader Aby K The Delhi Metro Rail Corporation (DMRC) yesterday issued a public notice (see below) in major newspapers indicating they’ll…
After TBM S52, workers from the Tata – Gülermak JV earlier this week also started lowering parts of TBM S53 into the 22m deep Bapu Bhawan Shaft adjacent…