9 Bidders for Delhi – Dehradun Expressway’s Phase 3 Package 2
9 construction firms today submitted bids to construct the 18.47 km Package…
9 construction firms today submitted bids to construct the 18.47 km Package…
Kalpataru Power Transmission Ltd. today emerged as the lowest bidder for the…
July 6, 2022 Update: Alstom Transport has been awarded Indore Metro and Bhopal…
February 9, 2023 Update: Consort Digital has been awarded a Rs. 89.85 crore…
May 28, 2022 Update: Segmental Consulting has been issued LOA with a contract…
November 14, 2022 Update: HMM Infra Ltd. has been issued a LOA contract valued…
Larsen & Toubro’s Tunnel Boring Machine Lavi (DZ672) on Friday was recommissioned…
Ceigall India Ltd. is the lowest bidder (L1) to construct the 25.24 km Southern…
Herrenknecht AG in April-end completed factory acceptance tests (FAT) on Larsen & Toubro’s second tunnel boring machine, TBM Shiv (S-1310A), for…
June 8, 2022 Update: Tender has been cancelled May 14, 2022 Original Post: Chennai Metro Rail Ltd. (CMRL) on Thursday received zero bids to supply 210…
10 firms / consortia have submitted bids to Gujarat Metro Rail Corporation (GMRC) for the construction of Ahmedabad Metro Phase 2 project’s 7.553 km…
JMC Projects today emerged as the lowest bidder to construct Kanpur Metro Phase 1’s second elevated section (Package KNPCC07) between Transport…
Alstom Transport on Saturday rolled out India’s first of 30 semi high-speed regional trains for National Capital Region Transport Corporation’s (NCRTC)…
Tata Projects Ltd. (TPL) this week emerged as the preferred bidder among 3 firms for the civil construction work of Noida International Airport at Jewar,…