Sudhir Power Wins Delhi Metro Phase 4’s 1st JICA Contract
March 5 Update: Sudhir Power Projects has been awarded DE-01’s Rs. 123.07 crore contract.
January 21 Original Post:
Sudhir Power Projects on Tuesday emerged as the lowest bidder for Delhi Metro Phase 4’s first of 44 civil & system packages which will be funded by Japan International Cooperation Agency (JICA).
This particular contract of the 65.1 km project deals with electrical & mechanical (E&M) works including fire suppression and diesel generator sets at the elevated viaducts of the 12.098 km Pink Line between Mukundpur and Maujpur, 19.85 km Magenta Line between Keshopur and Ashok Vihar, augmented Mukundpur Depot (expanded portion will house Magenta Line’s train-sets), and electrical works at new PWD flyovers en-route.
The Delhi Metro Rail Corporation (DMRC) had invited bids for it in October 2020 with an estimate of Rs 107.72 crore and completion period of 36 months. Technical bids were opened on December 22, 2020 to reveal 3 bidders.
Financial Bid Values:
Firm | Bid |
Sudhir Power Projects Ltd. | Rs. 128.23 crore |
Jakson Ltd. | Rs. 129.27 crore |
Blue Star Ltd. | Rs. 132.93 crore |
Package: DE-01 Lot 1
Brief Scope: Design Verification, SITC of E and M works, Fire Detection and Fire Suppression System including D.G. Sets for Elevated Corridors of Line – 7 Ext. , Line 8 Ext, Mukundpur Depot Augmentation Work i.e Electrification of PWD flyovers of Phase-IV of DMRC
Civil work on the Magenta Line’s elevated section is being carried out by CCECC – KEC JV (DC-01) and Gulermak – Sam (DC-03R), and on the Pink Line by Longjian – KEC JV.
Sudhir Power’s bid was roughly 19% higher than DMRC’s estimate, so this will go into a retender if negotiations to bring down its final contract value fail.
As I shared earlier – out of the 44 JICA-funded packages, I’m most looking forward to the last 4 civil packages (1 for Magenta Line and 3 for Silver Line), train-control and signaling package (DS-06) for the Silver Line, and the 288 coach (RS-17) rolling stock package. Tender notices for all of these are still pending.
Here’s a table with the status of all 11 Phase 4 E&M packages:
Package & Scope | Status |
DE-01: E&M for Line-7 Extn, Line 8 Extn and Mukundpur Depot Augmentation | Sudhir Power is Lowest Bidder among 3 |
DE-02: 25 KV FOCS and SCADA system at augmented Sarita Vihar Depot & Ajronda Depot | Technical Evaluation Underway (6 bidders) |
DE-03: E&M, TVS, BMS at Krishna Park Extn Station of Magenta Line (see details) | Bidding Underway (Technical Bids to be opened Jan 29) |
DE-04: RSS for Phase 4’s 3 lines | Tender Notice Pending |
DE-05: 25 KV AC OHE & SCADA at Krishna Park Exn Station of Magenta Line (see details) | Bidding Underway (Technical Bids to be opened Jan 28) |
DE-06: Unknown | N/A |
DE-07: Escalators on Lease | Bidding Underway (Technical Bids to be opened Jan 28) |
DE-08: Underground Corridors’ Traction | Tender Notice Pending |
DE-09: E&M, ECS/TVS & DG Sets of Underground Stations | Tender Notice Pending |
DE-10: E&M, ECS/TVS & DG Sets of Underground Stations | Tender Notice Pending |
DE-11: E&M, ECS/TVS & DG Sets of Underground Stations | Tender Notice Pending |
For more updates on India’s metro systems, check out my Home Page!
– TMRG
Any update on tkd ,arocity corridor silver line.??!
Go to pusp vihar you will find atleast 36 u girders are ready .and 4are casting and 0 launched.
Infrastructure is (infra super fast ture ) since 2014.Modi Modi Modi Gadkari Gadkari Gadkari❤️🙏😎😀👍🏿
Phase 4 is Metro’s most important line.
Infrastructure ko chod ke koi kaam nahi kiya hai Modi ne.
No politics, please!
Infrastructure is the amongst the most important works that is required for the development of nation and modi is doing just fine much better than his predecessors.