KPIL Wins Delhi Metro Phase 4’s Electrification Contract DE-08
January 25, 2024 Update: DMRC has issued LOA and awarded a Rs. 279,26,71,779.84 contract to Kalpataru Projects International Ltd. (KPIL).
December 21, 2023 Original Post: Kalpataru Projects International Ltd. (KPIL, formerly KPTL) on Tuesday was declared as the lowest bidder for the 25 kV AC OHE traction contract of the Delhi Metro’s Phase 4 project‘s Magenta Line (Line-8 extension) and Silver Line (Line-10).
The scope of this package DE-08 includes commissioning 25 kV AC traction (Rigid OHE), 33KV Auxiliary Sub Stations (ASS), associated cabling and SCADA systems within the Magenta Line’s 7.46 km underground Package DC-05 (Derawal Nagar – RK Ashram) which is under construction by Afcons Infrastructure.
The scope also includes the entire 23.6 km Silver Line which will connect Aerocity – Tughlakabad via 16 stations. This includes 3 underground packages (DC-07, DC-08 & DC-09) where rigid OHE (ROCS) will be installed and 1 elevated package DC-04 where flexible OHE (FOCS) will be installed.
Delhi Metro Rail Corporation (DMRC) had invited bids for this contract in April 2023 with a 3 year deadline and Rs. 359.78 crore estimate. Technical bids were opened in July to reveal 6 bidders.
Financial Bid Values
Firm | Bid (Rs. Crore) |
Kalpataru Projects | 279.26 |
Rail Vikas Nigam Ltd. | 285.88 |
Larsen & Toubro | 297.00 |
Siemens | 298.26 |
IRCON International | 320.43 |
KEC International | 330.24 |
Brief Scope: Design, Detail Engineering, Manufacture, Supply, Installation, Testing and Commissioning of 25KV AC Traction (RIGID OHE), 33KV Auxiliary Sub Stations (ASS),Associated Cabling and SCADA Systems for Underground Corridors of Line-8 Ext. & Underground and Elevated corridor of Line-10 of Delhi Mass Rapid Transport System Project Phase-4
Kalpataru’s bid of Rs. 279.26 crore was well below DMRC’s estimate of Rs. Rs. 359.78 crore, so a contract should be awarded in the coming weeks.
This package is just one of the many electrification-related packages in Phase 4 – see a list of all packages and their contractors / status over here.
Back in April 2022, Siemens was awarded a similar contract for the electrification work on the Magenta Line’s 2.03 km underground Package DC-06 between Janakpuri West and Krishna Park Extension. That section is in an advanced stage of completion with track-work starting in September.
For more updates, check out the Delhi Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to all updates and support the site over here.
– TMRG
Hat-Tip: Sandip
Leave a Reply
Want to join the discussion?Feel free to contribute!