JKIL’s Delhi Metro TBM Shalini Records Breakthrough at Vasant Kunj
J Kumar Infraprojects (JKIL) on Wednesday celebrated tunnel boring machine (TBM) S64B’s tunnel breakthrough at Vasant Kunj Station of Delhi Metro’s 23.622 km Golden Line (Line-10) which will connect Aerocity – Tughalakabad via 15 stations.
This was TBM S64B (nicknamed TBM Shalini)’s very first tunnel breakthrough and the second breakthrough for Delhi Metro Phase 4 project’s 6.51 km Package DC-08 connecting Aerocity – Kishangarh.
S64B is a refurbished 6.61m diameter Terratec Earth Pressure Balance (EPB) machine and one of four machines deployed by J Kumar on DC-08. Back in 2018-2020, this Ø6.61m dual-mode Terratec TBM, then nicknamed as Godavari-4, was deployed by J Kumar – CRTG JV to build tunnels for Package UGC-05 of Mumbai Metro’s 33.5 km Line-3 (Aqua Line).
Following extensive refurbishment, the machine passed factory acceptance tests (FAT) in April 2023 at J Kumar’s yard in Mumbai’s Chenna village on Ghodbunder Road. In June 2023, it became the first machine of DC-08 to be lowered at Kishangarh Station’s west shaft for building a 1500m tunnel towards Vasant Kunj.
S64B built 1105 rings (1 ring = 1.4m) with an inner diameter of 5.8m at an average depth of 22.86m. Per the Delhi Metro Rail Corporation’s press release, the new tunnel has a minimum depth 15.48 m and maximum depth of 30.25m.

Delhi Metro Rail Corporation (DMRC) had awarded J Kumar with Phase 4’s Rs. 1611.74 crore contract for Package DC-08 in March 2022 with a 42 month deadline.
J Kumar’s 6.116 km Aerocity – Kishangarh section is on the western-end of the Golden Line and comprises of twin tunnels, and 4 stations at Aerocity, Mahipalpur, Vasant Kunj & Kishangarh from chainage (-) 760 mt. to 5356.285 mt.

S63B is one of J Kumar’s four Terratec TBMs working on Package DC-08 between Aerocity – Kishangarh. The others are S63B (Sonakshi), S94 and S111 (Narayani).

Work on the parallel tunnel was completed by TBM S63B (Sonakshi) in March 2025.
With this development, a total of 11 tunnel breakthroughs have been recorded so far for the Golden Line. From east to west: 3 by Afcons for Package DC-07, 6 by L&T for Package DC-09, and 2 by J Kumar on Package DC-08. Afcons recorded its third breakthrough earlier this month which I wasn’t able to cover – see images and details here on DMRC’s X account.
For more updates, check out the Delhi Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to all updates and support the site over here.
– TMRG
So, the 42 month deadline for DC 08 expires in September, I guess. Any idea how far behind schedule they are?
There’s a couple of missed events recently on this blog, but obviously we’re all very grateful for your coverage overall:
1. Gurugram new metro line general consultant chosen
2. Pune metro aqua line extensions on both sides approved by centre
3. Mumbai metro lots of contracts finalized
4. Lucknow metro line 2 gets PIB approval
5. Nagpur metro has a new small extension recently approved, idk if centre also needs to approve it or not
7. Kolkata metro yellow line construction contract went out for the part past the airport
8. Indore metro priority section finally open
9. Kanpur metro’s new section is open now