Mumbai Metro Aqua Line – Info, Route Map, Fares, Tenders & Updates

Menu: News & Construction Updates | Overview | Yellow Line | Red Line | Aqua Line | Green Line | Orange Line | Pink Line

Information

Mumbai Metro’s Line-3 (Aqua Line) is a 33.5 km partially operational metro line with 27 stations connecting Cuffe Parade – BKC –  Aarey JVLR.

12.69 km Phase 1 of Mumbai Metro’s Line-3 (Aqua Line) connecting BKC – Aarey JVLR was inaugurated by Prime Minister Narendra Modi on October 5 2024. Commercial operations began at 11 am on October 7, 2024.

Mumbai Metro Rail Corporation Limited (MMRC) is the nodal agency responsible for building this primarily-underground line, and was constituted as a JV of the Govt. of India (GOI) and the Government of Maharashtra (GOM) on a 50:50 sharing basis. The line will be operated and maintained by Delhi Metro Rail Corporation (DMRC) for a period of 10 years.

Line-3 was approved for construction by India’s central government on June 28, 2013 with an estimated cost of Rs. 23,136 crore. A majority of it (57.2%) is being financed through an official development assistance (ODA) loan of Rs. 13,235 crore from Japan International Cooperation Agency (JICA) with an interest rate of 1.15% for project activities, 0.01% interest rate for consulting services, and 30 years of repayment (including 10 years of grace period).

7 contracts for the construction of Line-3’s underground tunnels and stations were awarded in July 2016 (see contractor list at the bottom). Construction work began in January 2017 and the first of 17 tunnel boring machines (TBMs) began excavation in November 2017. The final TBM breakthrough was recorded in November 2022.

Line-3 will be connected to other metro lines, bus and suburban rail services through multiple interchanges throughout its north-south route. The line’s official colour as Aqua was revealed to the public on August 16, 2019 by the then incumbent chief minister.

Line-3’s Detailed Project Report (DPR) prepared by RITES in 2011 can be viewed here.

Current Status

12.69 km Phase 1 of Mumbai Metro’s Line-3 (Aqua Line) connecting BKC – Aarey JVLR was inaugurated by Prime Minister Narendra Modi on October 5 2024. Commercial operations began at 11 am on October 7, 2024.

DMRC will initially operate 9 trains with 96 roundtrips daily at a headway of 6 minutes and 40 seconds during peak hours. Fare (ticket prices) will range from Rs. 10 – 50.

Line-3’s Phase 2 (BKC – Acharya Atre Chowk in Worli) is expected to be opened in February 2025.

In August 2022, MMRC invited tenders to prepare a Detailed Project Report for extending the line by 2.5 km from Cuffe Parade to Navy Nagar in Colaba.

Key Figures

  • Estimated Cost: Rs. 23,136 crore
  • Estimated Daily Ridership: 17.0 Lakhs/Day (2021)
  • Under Construction: 33 km
  • On Hold: 0.5 km (Ramp – Aarey Colony Station)
  • Rolling Stock: 248 coaches (31 x 8) by Alstom capable of UTO (Unattended Train Operation) with GoA4

System Specifications

  • PHPDT: 39,000 (2021)
  • Rolling Stock Width & Axle Load: 3.2m & 17T
  • Top Speed: 90 kmph
  • Average Speed: 34 kmph
  • Track Gauge: Standard Gauge – 1435 mm
  • Electrification: 25 kV, 50 Hz AC OHE + regenerative braking system
  • Signalling: Alstom Urbalis 400 Communication-based Train Control (CBTC)

Line-3’s Route Information

Line-3 – Aqua Line: Cuffe Parade – BKC – SEEPZ – Aarey Colony

  • Length: 33.5 km
  • Type: Underground & At-Grade
  • Depot: Aarey Colony (tentative; possibly Kanjurmarg pending court’s decision)
  • Number of Stations: 27
  • Station Names: Cuffe Parade, Vidhan Bhavan, Churchgate, Hutatma Chowk, CSMT, Kalbadevi, Girgaon, Grant Road, Mumbai Central, Mahalaxmi, Science Museum, Acharya Atre Chowk, Worli, Siddhivinayak, Dadar, Shitladevi, Dharavi, Bandra Kurla Complex (BKC), Vidyanagri, Santa Cruz, CSIA Terminal 1 (Domestic Airport), Sahar Road, CSIA Terminal 2 (International Airport), Marol Naka, MIDC, SEEPZ and Aarey Colony (only at-grade station)

Line-3’s Route Map

Tunneling Works

Tunneling works were completed in November 2022 after all 42 breakthroughs were recorded. Here’s a list of all 7 underground civil packages with their final TBM breakthrough information:

  • Package UGC-01: Cuffe Parade – CST (4.25 km) – Final breakthrough recorded by TBM Surya-1 in May 2021
  • Package UGC-02: CST – Mumbai Central (4.049 km) – Final breakthrough recorded by TBM T59 (Vaitarna-2) in April 2020
  • Package UGC-03: Mumbai Central – Worli – Final breakthrough recorded by TBM 1238 (Tansa-1) in November 2022
  • Package UGC-04: Worli – Dharavi (6.08 km) – Final breakthrough recorded by TBM S1073 (Krishna-1) in December 2020
  • Package UGC-05: Dharavi – MVS near CSIA T1 (4.94 km) – Final breakthrough recorded by TBM S64 (Godavari-4) in August 2020
  • Package UGC-06: Santa Cruz MVS – CSI T2 (4.45km) – Final breakthrough recorded by T62 (Tapi 2) in February 2021.
  • Package UGC-07: CSIA T2 – Sariput Ramp (4.157 km) – Final breakthrough recorded by TBM D213 (Wainganga-2) in December 2019.

Fares (Ticket Prices)

Fare (ticket prices) on Phase 1 of Mumbai Metro’s Line-3 range from Rs. 10 – 50. Fare prices between any two stations can be checked here.

Tenders

Latest notices inviting tenders can be viewed on MMRCL’s website. News on these notices, their bidders, awarded tenders and contracts are covered in further detail on the news & construction page.

Line-3’s Contractors

ContractContractor
General ConsultantMAPLE: AECOM (lead) – PADECO, LBG and Egis Rail
Operations & MaintenanceDelhi Metro Rail Corporation (DMRC)
UGC-01: Cuffe Parade – CST (tunnels & 4 stations)Larsen & Toubro – Shanghai Tunnel Engineering Co (L&T-STEC) JV
UGC-02: CST – Mumbai Central (tunnels & 4 stations)Hindustan Construction Co – Moscow Metrostroy JV
UGC-03: Mumbai Central – Worli (tunnels & 5 stations)Doğuş – Soma JV
UGC-04: Worli – Dharavi (tunnels & 3 stations)Continental Engineering Corp – ITD Cementation – Tata Projects JV
UGC-05: Dharavi – CSIA T1 (tunnels & 4 stations)J Kumar Infraprojects – China Railway Tunnel Group JV
UGC-06: CSIA T1 – Marol Naka
(tunnels & 3 stations)
J Kumar Infraprojects – China Railway Tunnel Group JV
UGC-07: Marol Naka – Aarey Colony Ramp (tunnels & 3 stations)Larsen & Toubro – Shanghai Tunnel Engineering Co (L&T-STEC) JV
Package 8: Aarey Colony DepotSam (India) Builtwell Pvt. Ltd.
Package 9-1: CNC Under Floor Wheel LatheHYT Engineering Company Pvt. Ltd.
Package 9-2: Battery Operated ShunterNITEQ – Renmakch JV
Package 10B: Track-works (main-line)Larsen & Toubro Ltd.
Package 10C: Track-works (within depot)Larsen & Toubro Ltd.
Package 11A: Traction System (25 kV Overhead Contact)Alstom Transport – Alstom Transport India Ltd. JV
Package 11B: Power Supply SystemLarsen & Toubro Ltd.
Package 12: Signaling & Train Control, Platform Screen Doors, Telecommunication System and M&E SCADAAlstom Transport – Alstom Transport India Ltd. JV
Package 14: Automatic Fare Collection (AFC)Kalindee Rail Nirman (Texmaco) – Asis Elektronik VE Billisim (Kalindee – Asis JV)
Package 15: Tunnel Ventilation System (TVS) & Environmental Control System (ECS) – Aarey – BKCShanghai Tunnel Engineering Co. Ltd
Package 15: Tunnel Ventilation System (TVS) & Environmental Control System (ECS) – Phase 2 Lot 1: BKC – Mumbai CentralBlue Star Ltd.
Package 15: Tunnel Ventilation System (TVS) & Environmental Control System (ECS) – Phase 2 Lot 2: Mumbai Central – Cuffe ParadeVoltas Ltd.
Package 16A: Escalators – Lot E1: Aarey – DadarYuanda – Royal JV
Package 16A: Escalators – Lot E2: Siddhivinayak – Cuffe ParadeJohnson Lifts – SJEC JV
Package 16B: Escalators (Lifts) – Lot L1: Aarey – DadarIFE – CRANEX JV
Package 16B: Escalators (Lifts) – Lot L2: Siddivinayak – Cuffe ParadeYuanda – Royal JV
Package 17: Rolling Stock – 248 standard gauge coaches (31 x 8)Alstom Transport – Alstom Transport India Ltd. JV
NJ-1: Depot E&M WorksBlue Star Lt.d
NJ-2: Pylon Shifting WorksRavin – Ashtavinayaka JV
NJ-3: Independent Safety Assessor (ISA)Bureau Veritas Italia S.p.A

Click on ‘News & Construction Updates’ below for project news, progress and updates.

Menu: News & Construction Updates | Overview | Yellow Line | Red Line | Aqua Line | Green Line | Orange Line | Pink Line

Page last updated: October 16, 2024. Have a question or spot an error? Let me know here.