7 Bidders for Delhi – Meerut RRTS Line’s Electrification Contract
7 firms have submitted bids for the overhead electrification contract (Package…
7 firms have submitted bids for the overhead electrification contract (Package…
Som Projects Private Limited has started piling work to build an interchange…
Mumbai Metropolitan Region Development Authority (MMRDA) on Monday invited bids…
July 3 Update: Bombardier has been awarded the contract valued at approximately…
Workers from NCC Ltd. in Pune today completed launching precast segments on…
Here’s a post with images of an extremely detailed, cute and impressive…
Last week, Modern Prefab Systems Pvt. Ltd. in Bhillai, Chhatisgarh completed…
Following a small puja, workers and engineers from Longjian – KEC JV today…
Following a small inauguration event, workers from KEC International Ltd. today started casting their first U-Girder for a 12.375 km elevated extension…
Workers from NCC Ltd. over the past few weeks have assembled pieces of a bowstring (tied-arch) girder bridge for a vehicular railway overbridge (ROB) that…
Back on June 12, workers from TATA Projects Limited – China Harbour Engineering Company (TPL-CHEC) JV erected their 100th U-girder in Thane for packages…
3 firms have submitted bids for the Independent Safety Assessor (ISA) contract of the 82.15 km Delhi – Meerut RRTS line project, after officials…
Workers from ITD Cementation and Herrenknecht on Friday resumed tunneling work on Kolkata Metro’s east-west 16.34 km Line-2 three months after it had…
Delhi Metro Rail Corporation has commenced work for the preparation of a Detailed Project Report (DPR) for a 3 km extension of Noida Metro’s Aqua…