Pune Metro Phase 1 – Information, Route Map, Fares, Tenders & Updates

Menu: News & Construction Updates | Overview | Phase 1 Info | Line-3 InfoPhase 1 Extn Info | Phase 2 Info

31.254 km Pune Metro Phase 1 project’s Detailed Project Report (DPR) with 2 metro lines and 29 stations was prepared & submitted by the Delhi Metro Rail Corporation in July 2009, revised in January 2013, August 2014, and finally once again in November 2015 to reflect current prices.

Although the State Government approved the project in 2012, it had run into red tape, politics and opposition from local NGOs & activists over its mostly elevated nature. The project received a final approval from the Union Government’s Cabinet on December 7, 2016.

In January 2017, Nagpur Metro Rail Corporation Ltd. (NMRCL) was renamed to Maharashtra Metro Rail Corporation Ltd. (Maha-Metro) to execute Pune Metro’s Phase 1 project.

Construction work on Pune Metro Phase 1’s 9.25 km first section (PCMC – Range Hills) started in August 2017 by NCC Ltd. Commercial operations on the first 2 sections of Phase 1 were inaugurated by Prime Minister Narendra Modi on March 6, 2022. The final section (District Court – Swargate) was inaugurated on September 29 2024.

System Specifications

  • Top Speed: 80 kmph
  • Average Speed: 34 kmph
  • Track Gauge: Standard Gauge – 1435 mm
  • Electrification: 25 kV, 50 Hz AC OHE
  • Signalling: Communications-based Train Control (CBTC)

Key Figures

Operational: 31.25 km | Under Construction: 0 km

  • Estimated Daily Ridership: 6 lakh in 2027
  • Rolling Stock: 104 coaches (26 train-sets x 4) to be supplied by Titagarh Wagons

Pune Metro Phase 1 Lines (Operational)

Line-1 (Purple Line): Pimpri Chinchwad Municipal Corporation (PCMC) – Swargate

  • Length: 16.589 km
  • Type: Elevated & Underground
  • Elevated: PCMC – Range Hills Ramp: 11.570 km, 9 stations
  • Underground: Range Hills Ramp – Swargate: 5.019 km, 6 stations
  • Depot: Range Hills (13.27 hectares)
  • Number of Stations: 14
  • Station Names: PCMC, Tukaram Nagar, Bhosari, Kasarwadi, Fugewadi, Dapodi, Bopodi, Khadki, Range Hill, Shivaji Nagar, Civil Court, Budhwar Peth, Mandai, Swargate
  • Status: Entire line became operational on September 29, 2024 after a 3 stage opening.

Line-2 (Aqua Line): Vanaz – Ramwadi

  • Length: 14.665 km
  • Type: Elevated
  • Depot: Kothrud (12 hectares)
  • Number of Stations: 16
  • Station Names: Vanaz, Anand Nagar, Ideal Colony, Nal Stop, Garware College, Deccan Gymkhana, Sambhaji Park, PMC, Civil Court, Mangalwar Peth, Pune Railway Station, Ruby Clinic, Bund Garden, Yerawada, Kalyani Nagar, Ramwadi
  • Status: Entire line became operational on March 6 2024 after a 3 stage opening

Pune Metro Phase 1 Route Map

The embedded map below shows the location of all stations for Phase 1 (exact) and Line-3 (tentative), and can be zoomed into!

An official PDF route map of Pune Metro will be added here when available.

Phase 1 Project Overview Video

Pune Metro Phase 1 Status

The entire Pune Metro Phase 1 is expected to be completed and opened in March 2024, much later than its December 2021 deadline.

Pune Metro Fares (Ticket Prices)

Pune Metro Tenders

Latest Pune Metro (Maha-Metro) tender notices can be viewed on Maha-Metro’s website. News on these notices, their bidders, awarded tenders and contracts are covered in further detail on the news & construction page.

Pune Metro Phase 1’s Contractors

ContractContractor
General Consultant (GC)SYSTRA-AECOM-EGIS-RITES JV
Environmental Impact Assessment (EIA) and Environmental Mitigation Plan (EMP)RITES
Social Impact Assessment (SIA) Study and Social Management Implementation plan, rehabilitation & resettlement (RR policy) planM/s Centre for Market Research & Social Development Pvt. Ltd. and M/s Manavadhikar Samajik Manch
Detailed Design Consultant for 9 elevated stations between PCMC – Range Hills for Line-1AYESA Ingenieria y Arquitectura, S.A.U (Ayesa)
Detailed Design Consultant for 12 elevated stations between Vanaz  – Ramwadi for Line-2LKT Engineering Consultants Ltd. & Architect Hafeez Contractor
Reach 1: PCMC – Range Hills
(10.795 km viaduct’s construction for Purple Line)
NCC Ltd.
Reach 2: Vanaz – Civil Court
(7.150 km viaduct’s construction for Aqua Line)
NCC Ltd.
Reach 1: PCMC – Range Hills
(9 elevated stations’ construction on Purple Line)
HCC – Al Fara’a JV
Reach 2: Vanaz – Civil Court
(8 elevated stations’ construction on Aqua Line)
HCC – Al Fara’a JV
P1UGC-01: Range Hills Ramp – Budhwar Peth (2.5 km tunnels and 2 stations’s construction for Line-1)Gulermak – TPL Pune JV
P1UGC-02: Budhwar Peth  – Swargate (1.83 km tunnels and 3 stations’ construction for Line-1)Gulermak – TPL Pune JV
P1UG-04: Construction of TBM shafts at Agriculture College & Swargate, and Swargate StationJ Kumar Infraprojects
Reach 3: Civil Court – Ramwadi
(7.657 km viaduct’s construction for Aqua Line)
J Kumar Infraprojects
Reach 3: Civil Court – Ramwadi
(7 stations between Mangalwarpeth – Ramwadi on Aqua Line)
Afcons – SPCPL JV
25KV Flexible Overhead Catenary system (OCS / OHE) with 22/25 KV RSS/TSS for Priority Section (PCMC – Phugewadi) of Line-1Bright Power Projects (India) Pvt. Ltd.
Signalling & Train Control System of Phase 1Alstom Transport India Limited – Alstom Transport SA JV
25KV Flexible & Rigid Overhead Catenary System (OCS / OHE) and sectioning posts for rest of Phase 1Alstom Transport India Limited – Alstom Transport SA JV
Construction of maintenance depots at Range Hills & VanazURC Construction (URCC) Pvt. Ltd.
Receiving cum auxiliary main cum traction substations including high voltage cabling from grid substation, 33 KV cable network, ASS & SCADA systemSterling & Wilson Pvt. Ltd
Standard gauge track at Range Hills Depot and Reach-1 (PCMC – Range Hills)Apurvakriti Infrastructure Pvt. Ltd
Standard gauge track at Vanaz Depot and Reach-2 (Vanaz – Civil Court)Apurvakriti Infrastructure Pvt. Ltd
Design, supply, testing & commissioning of 104 coaches (34 train-sets of 3 coaches)Titagarh Wagons Limited and Titagarh Firema S.p.A.
Elevators & Escalators – Lot 1Johnson Lifts Private Limited
Elevators & Escalators – Lot 2Schindler India Pvt Ltd and Schindler (China) Elevator Company Ltd.
Line-1’s Tunnel Ventilation System (TVS), TVS-SCADA, Environmental Control System (ECS), ECS and E&M SCADA, LV Power SystemSterling and Wilson Pvt. Ltd.
Telecommunication SystemHoneywell Automation India Ltd.
EMV Based Open Loop Automated Fare Collection (AFC system)HDFC Bank Limited – Asis Elektronik ve Bilisim Sistemleri A.S. – Paycraft Solutions Private Limited
Machinery and Plants for 2 rolling stock depots at Range Hills and VanazURC – Swastik Overseas – Fabryka Obrabiarek Rafamet – Bertolotti Rail S.R.L. JV
Fabrication, supply and installation of signage and graphics for 9 stations (PCMC – Dapodi) on Line-1 and 4 stations (Vanaz – Garware College) on Line-2Satin Neo Dimensions Private Limited.
Supply of 3000 MT 60E1 (UIC 60) , 1080 Grade Head Hardened (HH) RailsJindal Steel & Power Ltd.
Supply of 6000 MT 60E1 (UIC 60) , 1080 Grade Head Hardened (HH) RailsMitsui & Co., Ltd
Design, manufacturing and supply of Standard Gauge 60E1 (UIC 60) TurnoutsVoestalpine VAE VKN India Pvt. Ltd.
X-Ray Baggage Scanners, Door Frame Metal Detectors (DFMC), Hand Held Metal Detectors (HHMD) at 30 stationsBharat Electronics Limited (BEL)
Full Height Platform Screen Doors (PSDs)KTK Group Company Ltd.

Pune Metro History (Key Dates)

Phase 1
• 6 March 2022: PCMC – Phugewadi (Purple Line) – 6 km
• 6 March 2022: Vanaz – Garware College (Aqua Line) – 4.35 km
1 August 2023: Phugewadi – Civil Court (Purple Line) – 8.03 km
1 August 2023: Garware College – Ruby Clinic Hall (Aqua Line) – 5.45 km
 6 March 2024: Ruby Clinic Hall – Ramwadi (Aqua Line) – 5.94 km
 29 September 2025: District Court – Swargate (Purple Line) – 3.30 km

Click on ‘News & Construction Updates’ below for project news, progress and updates.

Menu: News & Construction Updates | Overview | Phase 1 Info | Line-3 Info Phase 1 Extn Info | Phase 2 Info

Page last updated: September 30, 2024. Have a question or spot an error? Let me know here.