Afcons Wins Delhi – Meerut RRTS Line’s Package 8

Afcons Infrastructure today emerged as the lowest bidder for constructing the 5.68 km underground Package 8 of the 82.15 km Delhi – Meerut (RRTS) Line, after officials from the National Capital Region Transport Corporation (NCRTC) opened financial bids submitted by different infrastructure companies.

After the 5.6 km New Ashok Nagar Ramp – Anand Vihar – Sahibabad Ramp Package 4 in Delhi, for which STEC emerged as the lowest bidder in June, Package 8 is the second and final underground section of the line. It consists of 3 stations at Meerut Central, Bhaisali and Begumpul – and out of these – the ones at Meerut Central and Bhaisal will exclusively serve Meerut’s local metro system and be serviced by ten 3-coach Bombardier trains

NCRTC invited tenders for this package in February 2020 with an estimate of approximately Rs 1750 crore and expects the assigned contractor to complete work in 1310 days (3.6 years) from when the contract is awarded. Technical bids were opened in July to reveal 5 bidders. During technical bid evaluation – STEC was found to be technically non-compliant to the tender conditions, so their financial bid was not opened.

Financial Bid Values:

FirmBid
Afcons Infrastructure Ltd.Rs. 1529.10 cr
Larsen & Toubro (L&T) Ltd.Rs. 1602 cr
Yapı Merkezi İnşaat ve Sanayi A.Ş. – Tata Projects Ltd. (YM-TPL JV)Rs. 1620.33 cr
Gulermak Agir Sanayi Insaat ve Taahh. A.S. (Gulermak)Rs. 1707.50 cr
Shanghai Tunnel Engineering Co., Ltd. (STEC)Disqualified

Tender No: Package 8 – DM/CN/COR-OF/099

Scope: Online bids are invited for Package-8, Design and Construction of Tunnels by TBM from near Brahampuri DN Ramp to Begumpul UP Ramp and 3 Under Ground Stations at Meerut Central, Bhaisali & Begumpul by Cut & Cover Method including Architectural Finishing and Design, supply, installation, testing and commissioining of Electrical and Mechanical Systtems including Fire detection & suppression System and Hydraulic systems on Delhi – Ghaziabad – Meerut Corridor.

Route Map of Package-8: Brahampuri Ramp – Begumpul Ramp with the indicative location of its stations – view NCR RRTS info & map

If no issues arise during financial evaluation, then Afcons Infrastructure will go on to be awarded with Package 8’s contract with a completion period of 1310 days (3.6 years). After the 4.3 km Package 6 (Sarai Kale Khan – New Ashok Nagar), this is Afcons’ second major win for civil construction work on this semi high-speed rail line.

With this development, the likely contractors for all civil packages of the main-line’s construction are now known. Here’s the current status of each:

Package / SectionStatus
Package 1: Sahibabad Ramp – Ghaziabad Station (elevated, 2 stations)Under construction by KEC-CCECC JV
Package 2: Ghaziabad Station – Duhai EPE crossing (elevated, 2 stations)Under construction by APCO-CRFG JV
Package 3 Lot-1: Duhai (EPE) – Modi Nagar North (elevated, 2 stations)Under Construction by Larsen & Toubro
Package 3 Lot-2: Modi Nagar North – Shatabdi Nagar (elevated, 5 stations)Under Construction by Larsen & Toubro
Package 4: New Ashok Nagar Ramp – Anand Vihar – Sahibabad Ramp (underground, 1 station)STEC is Lowest Bidder (contract not yet awarded)
Package 5A: Duhai Depot / WorkshopVNC-KEC is Lowest Bidder
Package 5B: Modipuram Depot / WorkshopBid Notice Pending
Package 6: Sarai Kale Khan – New Ashok Nagar (elevated, 2 stations)Afcons Infra is Lowest Bidder
Package 7: Shatabdi Nagar – Brahampuri – Brahampuri DN Ramp (elevated, 1 station) AND Begumpul UP Ramp – MES Colony – Daurli – Meerut North – Modipuram (elevated, 4 stations)Larsen & Toubro is Lowest Bidder
Package 8: Brahampuri DN Ramp to Begumpul UP Ramp (underground, 3 stations)Afcons Infra is Lowest Bidder (this post!)
Package 9A: Multistoried Staff Quarters & ConnectivitySam India is Lowest Bidder

A list of all 25+ packages (civil & systems) and their status can be viewed here.

For more updates, check out the NCR RRTS section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

11 Responses to "Afcons Wins Delhi – Meerut RRTS Line’s Package 8"

  1. Subroto says:

    Package 4…Package 4 will make or break the project.

    Reply
  2. Himanshu Doria says:

    STEC is disqualified. I think they are going to again float tender for package-4

    Reply
    • Abhishek Threja says:

      As per my sources,it’s not disqualified yet. Ncrtc want tensions to settle down in next few months and then they award the tender.

      Reply
    • TMRG says:

      Disqualified just from Package 8, but not from 4.

      For 4 – Decision on retendering / awarding the work has not yet been taken. I hope they do soon because we’ve lost 4 months since bids were opened.

      Reply
  3. Rohan says:

    Day before yesterday in night I heard a news that C4 package of is awarded but in nhsrcl.in I visited and still it is in archived tender. So, is it awarded or still pending?

    Reply
  4. Syed minhajashraf says:

    Apply for civil engineer metro exp 5 years
    Total exp 15 years. What’s up 00919935868375
    If vacancy call or what’s up

    Reply
  5. Er.Mohd Mubeen says:

    Sir I have Passed out B.tech in Civil Branch
    And Having Experience 5+ Years Experience in Structural specially
    Please Consider Me

    Reply
  6. Er.Mohd Mubeen says:

    Sir I have Passed out B.tech in Civil Branch
    And Having Experience 5+ Years Experience in Structural specially
    Please Consider Me
    +919528639783
    Call or WhatsApp me

    Reply
  7. Ahmed khan says:

    S A crane services contact number 8194090402

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to TMRG Cancel reply

Your email address will not be published. Required fields are marked *